Nuclear Power in China
(Updated October 2015)
- Mainland China has 27 nuclear power reactors in operation, 24 under construction, and more about to start construction.
- Additional reactors are planned, including some of the
world's most advanced, to give more than a three-fold increase in
nuclear capacity to at least 58 GWe by 2020-21, then some 150 GWe by
2030, and much more by 2050.
- The impetus for increasing nuclear power share in China is increasingly due to air pollution from coal-fired plants.
- China’s policy is for closed fuel cycle.
- China has become largely self-sufficient in reactor design
and construction, as well as other aspects of the fuel cycle, but is
making full use of western technology while adapting and improving it.
- China’s policy is to ‘go global’ with exporting nuclear technology including heavy components in the supply chain.
Most of mainland China's electricity is produced from fossil fuels,
predominantly from coal. Two large hydro projects are recent additions:
Three Gorges of 18.2 GWe and Yellow River of 15.8 GWe. In 2012 gross
electricity generation was 4994 TWh (not including Hong Kong) on IEA
figures, this being 3785 TWh from coal, 86 TWh from gas, 97 TWh from
nuclear, 872 TWh from hydro, and 147 TWh from non-hydro renewables. Net
export to Hong Kong was 10 TWh, adding to its 39 TWh generation (27 TWh
from coal, 11 TWh from gas). Rapid growth in demand has given rise to
power shortages, and the reliance on fossil fuels has led to much air
pollution. The economic loss due to pollution is put by the World Bank
at almost 6% of GDP,1
and the new leadership from March 2013 has prioritised this.* Chronic
and widespread smog in the east of the country is attributed to coal
burning.
The State Council expected CNY 2.37 trillion ($380 billion) to be
spent on conservation and on emissions cuts in the five years through
2015. In August 2013 it said that China should reduce its carbon
emissions by 40-45% by 2020 from 2005 levels, and would aim to boost
renewable energy to 15% of its total primary energy consumption by 2020.
In 2012 China was the world’s largest source of carbon emissions – 2626
MtC (9.64 Gt CO2), and its increment that year comprised
about 70% of world total increase. In March 2014 the Premier said that
the government was declaring “war on pollution” and would accelerate
closing coal-fired power stations. In November 2014 the Premier
announced that China intended about 20% of its primary energy
consumption to be from non-fossil fuels by 2030, at which time it
intended its peak of CO2 emissions to occur.
The February 2015 edition of the BP Energy Outlook 2035
projects that by 2035 China becomes the world’s largest energy importer,
overtaking Europe, as import dependence rises from 15% to 23%. China’s
energy production rises by 47% while consumption grows by 60%. China’s
fossil fuel output continues to rise with increases in natural gas
(+200%) and coal (+19%) more than offsetting declines in oil (-3%).
China’s CO2 emissions increase by 37% and by 2035 will
account for 30% of world total with per capita emissions surpassing the
OECD by 2035.
The distribution of energy resources relative to demand poses some
challenges, notably for north-south coal transport and east-west power
transmission.
Electricity consumption in 2012 rose only 5.5% to 4.9 trillion
kWh, and it was expected to grow between 6.5% and 8.5% in 2013. In 2011
it rose 11.7% to 4693 billion kWh, according to the China Electricity
Administration. Its 2010 increase of 14.56% to 4190 billion kWh
corresponded with a 10% growth in GDP, according to the China
Electricity Council. Some 3090 billion kWh of this (74%) was in
industry.
Nuclear power contributed 2.4% of the total production in 2014 – 123.8 billion kWh according to the IAEA.
Per capita electricity consumption was 3510 kWh in 2012. By 2030 it is expected to be 5500 kWh/yr and by 2050 about 8500 kWh/yr.
Installed generating capacity at the end of 2012 reached 1145
GWe 19% up in two years. Capacity growth is expected to slow, reaching
about 1600 GWe in 2020, and 2000 GWe in 2025. Coal accounted for 59% of
the newly-added capacity in 2012.
At the end of 2010, fossil fuelled capacity (mostly coal) reached 707
GWe, hydro capacity was 213 GWe (up 16.6 GWe in the year), nuclear
capacity was 10.8 GWe and wind capacity reached 31 GWe. Investment in
electricity dropped to CNY 705 billion ($107 billion) for the year. A
2013 report from the NDRC said that China added 15 GWe of wind energy
capacity in 2012 and 3 GWe of solar. It endorsed targets to add 21 GWe
of hydroelectric capacity, 18 GWe of wind and 10 GWe of solar in
2013. Another 12 GWe of solar PV was added in 2014, making 28 GWe by
year end, and a target of 70 GWe for 2017 was announced. A further 100
GWe of wind capacity is expected over 2014-18.
These capacity increase figures were remarkable considering the
forced retirement of small inefficient coal-fired plants: 26 GWe of
these was closed in 2009 and 11 GWe in 2010, making 71 GWe closed since
2006, cutting annual coal consumption by about 82 million tonnes and
annual carbon dioxide emissions by some 165 million tonnes. China is
well advanced in developing and deploying supercritical and
ultra-supercritical coal plants, as well as moving quickly to design and
deploy technologies for integrated (coal) gasification combined cycle
(IGCC) plants. Nevertheless it consumed about 4.3 billion tonnes of coal
in 2013, more than half the world total, and coal comprised more than
70% of China’s primary energy. By 2020 it is expected to use some 5
billion tonnes of coal annually, while aiming to cut consumption in the
northern areas spanning Beijing, Hebei, and Tianjin.
The grid system run by the State Grid Corporation of China
(SGCC) and China Southern Power Grid Co (CSG) is sophisticated and
rapidly growing, utilising ultra high voltage (1000 kV AC and 800 kV DC)
transmission. By 2015 SGCC invested CNY 500 billion ($75.5 billion) to
extend the UHV grid to 40,000 km, and in 2015 it plans to spend CNY 420
billion, 24% up on 2014. It expects to commission 46,000 km of AC
transmission in 2015, along with UHV lines, and start building 13,000 km
of DC lines. SGCC plans to start pre-project work on transmission links
with Kazakhstan, Russia, Mongolia and Pakistan in 2015. It is also
building a major UHV DC project in Brazil.
By 2020, the capacity of the UHV network is expected to be some 300
GW, which will function as the backbone of the whole system, connecting
six regional clusters. By 2020 there will be 400 GWe of clean energy
sources connected, of which hydropower will account for 78 GW, and wind
power from the north a further significant portion. At present up to
half of the wind output is wasted – 2.8 TWh in 2012, because of limited
grid connections, according to a China Daily report. At the end
of 2009, China had budgeted to spend $600 billion upgrading its grid.
Over 2014 to 2020 high-voltage transmission lines are expected to
increase from 1.15 million circuit km to 1.6 million circuit km, in line
with a big increase in generation capacity (from 1371 to 2073 GWe
according to one forecast), and operational transmission losses are
expected to be 5.7%, down from 6.6% in 2010.
Among the main listed generators, Huaneng Power produced 203.5
billion kWh from its domestic plants in 2009, 10.2% up on 2008. Datang
Power produced 141.9 billion kWh, 12% up on 2008. Huadian Power produced
107.5 billion kWh, 6.75% above 2008. CPI Development produced 43.9
billion kWh, 2.0% above 2008 level. The main nuclear operators are China
National Nuclear Corporation (CNNC) and China General Nuclear Power
Group (CGN).
Electricity generation is only one part of China's rapid development;
roads, air transport and a 16,000 km high-speed rail system (powered by
electricity) by 2020 are others. A record 486 km/h rail speed between
Beijing and Shanghai was achieved in 2010, and by January 2011, 8358 km
of 200 km/hr+ track was operational. By the end of 2011, 13,073 km of
such track is expected to be in service after further investment of CNY
700 billion ($106 billion). Also the world's longest bridge – the 42 km
Qingdao Haiwan bridge in Shandong province is being built.
Energy policy and clean air
While coal is the main energy source, most reserves are in the north
or northwest and present an enormous logistical problem – nearly half
the country's rail capacity is used in transporting coal. Because of the
heavy reliance on old coal-fired plant, electricity generation accounts
for much of the country's air pollution, which is a strong reason to
increase nuclear share. China has overtaken the USA as the world's
largest contributor of carbon dioxide emissions.* Gas consumption in
2013 was forecast to be 165 billion cubic metres, up 11.9% on
2012. China has shale gas resources, but much of it is in the northwest
which is very arid, so water supply is a constraint. By 2035 the US
Energy Information Administration expects China’s gas to come equally
from conventional, coal bed and shale sources.
Water is also a constraint on coal-fired power generation, much of
which is in water-deficient regions. Retrofit to air cooling decreases
efficiency by 3-10% and is reported to cost about $200 million per GWe
in China.
China's energy consumption per unit of gross domestic product met a
target reduction of 20% from 2005 levels by the end of 2010, according
to the National Development and Reform Commission (NDRC).
In March 2013 the NDRC announced new plans for seawater
desalination.* China aims to produce 2.2 million m3/day of desal water
by 2015, more than three times the 2011 level. More than half of the
freshwater channelled to islands and more than 15% of water delivered to
coastal factories will come from the sea by 2015, according to the
plan.
A white paper on Energy Policy was released by the State Council on
24 October 2012. This included raising the proportion of clean,
low-carbon fossil energy and non-fossil energy in the energy mix, and
promoting the efficient and clean utilization of coal. It aims to
increase the shares of non-fossil fuels in primary energy consumption.
"China will invest more in nuclear power technological innovations,
promote application of advanced technology, improve the equipment level,
and attach great importance to personnel training. China's installed
capacity of nuclear power is expected to reach 40 GWe by 2015." The
installed generating capacity of wind power is expected to reach 100 GWe
by the end of 2015, and that of solar energy is expected to exceed 21
GWe by then, with a total solar heat collection area of 400 million
square metres.
In September 2014 a national climate change plan prepared by NDRC was
approved by the State Council. This set emission and clean energy
targets for 2020. The carbon emission intensity target is 40-45%
reduction from 2005 to 2020, with good progress of almost 29% by the end
of 2013. It aims to increase the shares of non-fossil fuels in primary
energy consumption to about 15% by 2020 – at the end of 2013 it was
9.8%. The plan also sets the target for China to increase forest
coverage by 40 million hectares within the next five years to 2019. The
government said it would speed up efforts to establish a carbon emission
permit market, as well as deepening international cooperation under the
principles of "common but differentiated responsibilities," equity, and
respective capability. UN emission reduction targets after 2020 are
likely to be addressed in the 13th Five-Year Plan about 2016.
The State Council published the Energy Development Strategy Action Plan, 2014-2020
in November 2014. The plan aims to cut China's reliance on coal and
promote the use of clean energy, confirming the 2012 target of 58 GWe
nuclear in 2020, with 30 GWe more under construction. The plan calls for
the "timely launch" of new nuclear power projects on the east coast and
for feasibility studies for the construction of inland plants. It says
that efforts should be focused on promoting the use of large pressurized
water reactors (including the AP1000 and CAP1400 designs), high
temperature gas-cooled reactors (HTRs) and fast reactors. It also says
that research should be conducted to "improve the nuclear fuel cycle
system” including reprocessing of used fuel.
More broadly, the
share of non-fossil fuels in the total primary energy mix should
increase from 9.8% in 2013 to 15% in 2020, while coal’s share shrinks
from 67% to 62%, according to the plan. Installed generating capacity of
hydro, wind and solar power is expected to reach 350 GWe, 200 GWe and
100 GWe, respectively, by 2020.
In June 2015 China submitted its Intended Nationally Determined
Contribution (INDC) to climate change mitigation and adaptation for 2020
to 2030 to the UN. This pledge included increasing the share of
non-fossil fuels in primary energy consumption to about 20% and
restraining carbon emissions in 2030 to double of those in 2005 (after
being 158% of the 2005 level in 2015 and 182% in 2020). Annual average
new nuclear capacity 2005 to 2020 is 3.4 GWe/yr, from 2020 to 2030 it is
9.0 GWe/yr.
Nuclear power
Nuclear power has an important role, especially in the coastal areas
remote from the coalfields and where the economy is developing rapidly.
Generally, nuclear plants can be built close to centres of demand,
whereas suitable wind and hydro sites are remote from demand. Moves to
build nuclear power commenced in 1970 and about 2005 the industry moved
into a rapid development phase. Technology has been drawn from France, Canada and Russia,
with local development based largely on the French element. The latest
technology acquisition has been from the USA (via Westinghouse, owned by
Japan's Toshiba) and France. The State Nuclear Power Technology
Corporation (SNPTC) has made the Westinghouse AP1000 the main basis of
technology development in the immediate future, particularly evident in
the local development of CAP1400 based on it.
This has led to a determined policy of exporting nuclear technology,
based on China’s development of the CAP1400 reactor with Chinese
intellectual property rights and backed by full fuel cycle capability.
The policy is being pursued at a high level politically, as one of 16
key national science & technology projects, utilising China's
economic and diplomatic influence, and led by the initiative of CGN
commercially, with SNPTC and most recently CNNC in support.
By around 2040, PWRs are expected to level off at 200 GWe and fast
reactors progressively increase from 2020 to at least 200 GWe by 2050
and 1400 GWe by 2100.
Prior to 2008, the government had planned to increase nuclear
generating capacity to 40 GWe by 2020 (out of a total 1000 GWe planned),
with a further 18 GWe nuclear being under construction then. However,
projections for nuclear power then increased to 70-80 GWe by 2020, 200
GWe by 2030 and 400-500 GWe by 2050. Following the Fukushima accident
and consequent pause in approvals for new plants, the target adopted by
the State Council in October 2012 became 60 GWe by 2020, with 30 GWe
under construction. In 2015 the target for nuclear capacity on line in
2030 was 150 GWe, providing almost 10% of electricity, and 240 GWe in
2050 providing 15%. However the post-Fukushima slowdown may mean that
the 2030 figure is only about 120 GWe.
National policy has moved from ‘moderate development’ of nuclear
power to ‘positive development’ in 2004, and in 2011-12 to ‘steady
development with safety’. See further comment under Post-Fukushima Review
below. Then in 2014 the NEA announced that it was aiming for world
leadership in nuclear technology, with detailed plans to come in April
2015. The precise direction and priorities of such plans are likely to
be strongly contested among the likely players, notably CNNC, CGN and
SNPTC (now SNPI).
In December 2011 the National Energy Administration (NEA) said that
China will make nuclear energy the foundation of its power-generation
system in the next "10 to 20 years", adding as much as 300 GWe of
nuclear capacity over that period. Two weeks earlier the NDRC
vice-director said that China would not swerve from its goal of greater
reliance on nuclear power. In September 2013 SNPTC estimated that 4-6
new units per year would be needed to 2015 then 6-8 units during the
13th Five-Year Plan Period (2016-2020), increasing to 10 units each year
after 2020. In December 2014 the NEA said that China could manufacture
eight full sets of reactor equipment per year.
In September 2010, the China Daily reported that China
National Nuclear Corporation (CNNC) alone planned to invest CNY 800
billion ($120 billion) into nuclear energy projects by 2020. In order
to fund the company's expansion target, CNNC planned to list its
subsidiary, CNNC Nuclear Power Co Ltd in 2011, to attract strategic
investors, but this apparently did not occur.
In July 2013 the NDRC set a wholesale power price of CNY 0.43 per kWh
(7 US cents/kWh) for all new nuclear power projects, to promote the
healthy development of nuclear power and guide investment into the
sector. The price is to be kept relatively stable but will be adjusted
with technology advances and market factors, though many consider it not
high enough to be profitable. It is reported that the price for power
from Sanmen may in fact be about 5% higher. Nuclear power is already
competitive, and wholesale price to grid has been less than power form
coal plants with flue gas desulfurization, though the basic coal-fired
cost is put at CNY 0.3/kWh*. In March 2015 a new round of electricity
market reform was launched, which allowed nuclear power companies to
negotiate prices with customers. This is expected to help get inland
projects moving ahead.
Hong Kong supply
Hong Kong gets much of its power from mainland China, in particular
about 70% of the output from Daya Bay's 1888 MWe net nuclear capacity is
sent there. A 2014 agreement increases this to 80%. The Hong Kong
government plans to close down its coal-fired plants, and by 2020 to get
50% of its power from mainland nuclear (now 23%), 40% from gas locally
(now 22%) and 3% from renewables. Another option, with less import
dependence, is to increase domestic generation from gas to 60%, and
maintain mainland nuclear at 20%.
Hong Kong utility China Light & Power has equity in CGN's Daya
Bay (25%) power plant, is negotiating concerning a possible 17% share in
Yangjiang, and may take equity in a further CGN nuclear plant. Since
1994 it has been getting up to one-third of its power from Daya Bay
output, and this contract now runs to 2034. According to CLP data,
nuclear power cost HK 47 c/kWh in November 2013, compared with 27 cents
for coal and 68 cents for gas, which provides the main opportunity to
increase supply.
Regulation and safety – general
The National Nuclear Safety Administration (NNSA) under the China
Atomic Energy Authority (CAEA) was set up in 1984 and is the licensing
and regulatory body which also maintains international agreements
regarding safety. It reports to the State Council directly, but is
perceived to be insufficiently independent of the CAEA, which plans new
capacity and approves feasibility studies for new plants (see also SCRO
report below). In relation to the AP1000, NNSA works closely with the US
Nuclear Regulatory Commission.
NNSA is responsible for licensing all nuclear reactors and other
facilities, safety inspections and reviews of them, operational
regulations, licensing transport of nuclear materials, waste management,
and radiation protection including sources and NORM. It licenses staff
of nuclear manufacturers through to reactor operators. It is responsible
for environment impact assessment of nuclear projects. The 2003 Law on
Prevention and Control of Radioactive Pollution passed by Congress is
supplemented by a number of Regulations issued over 1986 to 2011 with
the authority of State Council.
Nuclear power plant licences issued by NNSA progress from siting
approval, then construction permit (12 months before first concrete),
fuel loading permit, to operation licence.
China has shown unprecedented eagerness to achieve world's best
standards in nuclear safety (as also in civil aviation). It has
requested and hosted 12 Operational Safety Review Team (OSART) missions
from IAEA teams to October 2011, and each plant generally has one
external safety review each year, either OSART, WANO peer review, or
CNEA peer review (with the Research Institute for Nuclear Power
Operations, RINPO). In December 2013 the NNSA with its Japanese and
South Korean counterparts agreed to form a network to cooperate on
nuclear safety and quickly exchange information in nuclear
emergencies. NNSA is also part of the ASEAN+3 Forum on Nuclear Safety.
In 2013 the CAEA signed a cooperation agreement with the OECD’s
Nuclear Energy Agency (NEA), confirming China as a ‘key partner’ with
OECD.
Following the Fukushima accident in Japan in March 2011, the
government suspended its approval process pending a review of lessons
which might be learned from it, particularly regarding siting of
reactors with plant layout, and control of radiation release. Safety
checks of operating plants were undertaken immediately, and review of
those under construction was completed in October 2011. Resumption of
approvals for further new plants was suspended until a new nuclear
safety plan was accepted and State Council approval given in October
2012 (see also Post-Fukushima review below).
Following the Fukushima accident, concern regarding possible river
pollution and depletion during droughts (due to evaporative cooling
towers) meant delays until at lest 2015 to the inland AP1000 plants
which were due to start construction in 2011.
SCRO report on nuclear investment and safety
In January 2011 a report from the State Council Research Office
(SCRO), which makes independent policy recommendations to the State
Council on strategic matters, was published. While approving the
enormous progress made on many fronts, it cautioned concerning
provincial and corporate enthusiasm for new nuclear power plants and
said that the 2020 target should be restricted to 70 GWe of new plant
actually operating so as to avoid placing undue demand on quality
control issues in the supply chain. Another 30 GWe could be under
construction. It emphasised that the priority needed to be resolutely on
Generation-III technology, notably the AP1000 and derivatives. However,
ambitious targets to deploy AP1000s with reduced foreign input had
proved difficult, and as a result, more of the Generation-II CPR-1000
units are under construction or on order. Only China is building Gen-II
units today in such large numbers, with 57 (53.14 GWe) on the books4.
SCRO said that reactors built today should operate for 50 or 60
years, meaning a large fleet of Gen-II units will still be in operation
into the 2070s, when even Gen-III reactors would have given way to
Generation-IV and perhaps even to commercial nuclear fusion. The country
should be 'careful' concerning 'the volume of second generation units
under construction... the scale should not be too large' to avoid any
perception of being below international standards of safety in future,
when most of the world's Gen-II reactors are retired. The SCRO noted the
100-fold increase in probabilistic safety brought by Gen-III, and that
future generations would continue the trend.
Another factor potentially affecting safety is the nuclear power
workforce. While staff can be technically trained in four to eight
years, 'safety culture takes longer' at the operational level. This
issue is magnified in the regulatory regime, where salaries are lower
than in industry, and workforce numbers remain relatively low. SCRO said
that most countries employ 30-40 regulatory staff per reactor in their
fleet, but the National Nuclear Safety Administration (NNSA) has only
1000 staff – a figure that must more than quadruple by 2020. The SCRO
recommended that 'The NNSA should be an entity directly under the State
Council Bureau, making it an independent regulatory body with
authority.' It is currently under the China Atomic Energy Authority,
although it is understood to report to the State Council directly
The report said that 32 further reactors 34.86 GWe had been approved
by the state at end 2010, with 25 (27.73 GWe) then under construction.
The SCRO calculated that nuclear development would require new
investment of some CNY 1 trillion ($151 billion) by 2020, not counting
those units being built now. These projects rely mainly on debt, funds
are tight, and 'investment risks cannot be discounted'. This cost figure
could rise if supply chain issues impact schedules, with repercussions
for companies borrowing to build and for the economics of the Chinese
nuclear program overall. A major recommendation was to sort out
bottlenecks in the supply chain for AP1000 reactors.
Post-Fukushima review
Following the Fukushima accident in March 2011, the State Council,
announced on March 16 that it would suspend approvals for new nuclear
power stations and conduct comprehensive safety checks of all nuclear
projects, including those under construction (with an immediate halt
required on any not satisfactory). It also suspended work on four
approved units due to start construction in 2011*. About 34 reactors
were already approved by the central government of which 26 were being
built. The Shidaowan HTR, though ready for first concrete, was also
delayed. After three months the inspections of operating plants had been
completed, and those on plants under construction were completed by
October (though construction had continued).
In May 2012 a new safety plan for nuclear power was approved in
principle. The State Council considered a report on civil nuclear
facilities including changes made since the Fukushima accident, and
affirmed that the fundamental principle of China’s nuclear safety and
radioactive pollution prevention is to put safety and quality first. It
is now explicit that Chinese regulations are to fully incorporate the
safety standards of the International Atomic Energy Agency (IAEA). In an
unprecedented move to improve the transparency of nuclear regulation
the government then formally solicited public comments on its nuclear
safety plan which must ensure that no ‘serious incident’ (INES Level 3)
or greater occurs at any reactor. So far in China no nuclear incident
has been over INES level 2. The plan involves significant expenditure
across all of the country’s facilities.
On 24 October 2012 the premier outlined a modified approach to
nuclear power construction at a State Council meeting, signaling that
approvals for new plants could recommence. Construction of 25 reactors
had continued following March 2011, and several are now on line. He said
that nuclear power development would continue at a steady pace, with
safety paramount so that that new reactors will have to comply with
new-generation safety standards, and plans for inland plants would be
put on hold until 2015. The nuclear capacity target for 2020 became 58
GWe in operation and 30 GWe under construction. Over 2013-15, 13 GWe was
to be added, and over 2016-20, 30 GWe more. Review of these figures in
May 2015 suggests that the 58 GWe might take until 2021, with 30-35 GWe
under construction then.
State Council approved the "12th 5-year Plan for Nuclear Safety and
Radioactive Pollution Prevention and Vision for 2020", compiled by the
Ministry of Environment. It suggested that China will need to spend RMB
80 billion ($13 billion) on improving nuclear safety at 41 operating and
under construction reactors over the next three years to 2015. "China
has multiple types of nuclear reactors, multiple technologies and
multiple standards of safety, which makes them hard to manage," it said,
adding that the operation and construction of nuclear reactors must
improve. The chairman of CNNC commented that it was not technology or
finance now holding back the sector in China, but the need to gain
public acceptance, especially for inland projects. Nevertheless, "the
pace of approvals will certainly be slower but the overall direction
cannot be changed," he said. Further details followed the 18th National
Congress in 2012.
The bottom line of safety requirements is that radioactive releases
should never cause “unacceptable effects on the environment or the
public”, and that advanced nuclear technology should “practically
eliminate the possibility of release of significant quantities of
radioactive substances from nuclear power units” built from 2016.
A series of research and development (R&D) projects was launched
by the NEA in February 2012 to improve safety-related technology and the
country’s emergency response capabilities at indigenous nuclear power
plants in the event of an extreme disaster beyond design basis. The 13
R&D projects were conducted by CNNC, CGN and the Institute of
Nuclear and New Energy Technology (INET) at Tsinghua University. They
include the development of passive emergency power supply and cooling
water systems, development of passive containment heat removal systems,
developing hydrogen control devices, measures for the prevention and
mitigation of used fuel accidents, and analysing the impact of multiple
simultaneous external events and response measures. Other projects
studied the monitoring and treatment of contaminated ground and water.
All were expected to be complete in 2013. Referring particularly to the
CPR-1000 reactors being widely built in China, the National Energy
Administration (NEA) said that "Implementing the measures will
comprehensively enhance safety of Generation II+ nuclear power
technology in our country, and significantly reduce the core damage
frequency and large early release frequency" to "internationally
recognized levels" required for Generation III reactors. The outcome of
this is the ACC1000 reactor design described below.
In July 2010 a 22-strong IAEA team from 15 countries carried out a
two-week Integrated Regulatory Review Service mission to review of
China's regulatory framework for nuclear safety. The IAEA made a number
of recommendations but said that the review had provided "confidence in
the effectiveness of the Chinese safety regulatory system and the future
safety of the vast expanding nuclear industry."
In 2014, the five major nuclear power utilities including CNNC and CGN signed the Cooperation Framework Agreement on Mutual Aid for Nuclear Accident Emergency Among Groups,
undertaking to establish and improve the emergency response mechanism
and cooperation between adjoining nuclear power plants belonging to
different groups, in case of a serious nuclear accident.
Sites of Nuclear Power Plants in China
Reactor technology
China has set the following points as key elements of its nuclear energy policy:
- PWRs will be the mainstream but not sole reactor type.
- Nuclear fuel assemblies are fabricated and supplied indigenously.
- Domestic manufacturing of plant and equipment will be maximised, with self-reliance in design and project management.
- International cooperation is nevertheless encouraged.
The technology base for future reactors remains officially undefined,
though two designs are currently predominant in construction plans:
CPR-1000 and AP1000, though plans for the former have been scaled back
post-Fukushima. Beyond them, high-temperature gas-cooled reactors and
fast reactors appear to be the main priorities.
A major struggle between the established China National Nuclear
Corporation (CNNC) pushing for indigenous technology and the small but
well-connected State Nuclear Power Technology Corp (SNPTC) favouring
imported technology was won by SNPTC about 2004. In particular, SNPTC
proposed use of indigenized 1000+ MWe plants with advanced
third-generation technology, arising from Westinghouse AP1000 designs at
Sanmen and Haiyang (see section below on Embarking upon Generation III plants).
Westinghouse has agreed to transfer technology to SNPTC over the first
four AP1000 units so that SNPTC can build the following ones on its
own. In 2014 SNPTC signed a further agreement with Westinghouse to
deepen cooperation in relation to AP1000 and CAP1400 technology globally
and “establish a mutually beneficial and complementary partnership”.
In February 2006, the State Council announced that the large advanced
PWR was one of two high priority projects for the next 15 years,
depending on "Sino-foreign cooperation, in order to master international
advanced technology on nuclear power and develop a Chinese
third-generation large PWR".5
In September 2006, the head of the China Atomic Energy Authority said
that he expected large numbers of third-generation PWR reactors derived
from foreign technology to be built from about 2016, after experience is
gained with the initial AP1000 units.
This trend was given impetus by the reappraisal of safety following the Fukushima accident.
EPR
Two Areva EPR reactors are being built at Taishan, and two more are planned. (see section below on Embarking upon Generation III plants.) Areva says the reactors are 4590 MWt, with net power 1660 MWe.
In October 2008, Areva and CGN (then: CGNPC) announced establishment
of an engineering joint venture as a technology transfer vehicle for
development of the EPR and possibly other PWR plants in China and later
abroad. The Wecan JV, 55% CGN subsidiary China Nuclear Power Engineering
Co. and 45% Areva, was set up in December 2009 and based in Shenzhen,
though by mid-2011 the CGN share was held by China Nuclear Power
Technology Research Institute (CNPRI), another subsidiary. Overseas
projects involving CGN appear now to hold the only potential for
expanding the role of Areva’s EPR technology involving China.
AP1000, CAP1000
The Westinghouse AP1000 is the main basis of China's move to
Generation III technology, and involves a major technology transfer
agreement. It is a 1250 MWe gross reactor with two coolant loops. The
first four AP1000 reactors are being built at Sanmen and Haiyang, for
CNNC and China Power Investment Corp (CPI) respectively. Six more at
three sites are firmly planned after them, at Sanmen, Haiyang and Lufeng
(for CGN), and at least 30 more are proposed to follow. A State Council
Research Office report in January 2011 emphasised that these should
have priority over alternative designs such as CPR-1000, and this
position strengthened following the Fukushima accident.
The reactors are built from modules fabricated adjacent to each site.
The timeline is 50 months from first concrete to fuel loading, then six
months to grid connection for the first four units, with this expected
to reduce significantly for the following units. In October 2009, SNPTC
and CNNC signed an agreement to co-develop and refine the AP1000 design,
and this position strengthened following the Fukushima accident. (See
also section below on Embarking upon Generation III plants).
CNEA estimated in May 2013 that the construction cost for two AP1000
units at Sanmen are CNY 40.1 billion ($6.54 billion), or 16,000 Yuan/kW
installed ($2615/kW), instead of CNY 32.4 billion earlier estimated.
This is about 14% higher than the latest estimate for the CPR-1000, but
likely to drop to about CNY 13,000/kW ($2120/kW) with series
construction and localisation as envisaged. Grid purchase price is
expected to exceed CNY 0.45/kWh at present costs, and drop to the
standard CNY 0.43/kWh with series build and reduced capital cost.
SNPTC also refers to a CAP1000, which is a local standardization of
the design, transitional to CAP1400. It is said to have reduced cost and
improved operation and maintenance attributes. The base design,
commenced in 2008, is complete, the detailed design, started in April
2010, was due by June 2013. Early in 2012 SNPTC had organized SNERDI
(nuclear island and general designer) and SNPDRI (for conventional
island) to localize the design for both inland and coastal sites, for
Xianning, Pengze and Taohuajiang.
Alstom has an agreement with Dongfang Electric Corporation for
turbine and generator packages for future AP1000 projects to be based on
Alstom’s Arabelle technology. Alstom and DEC have supplied more than
half of the turbine generator sets for Chines nuclear power plants to
2013.
CAP1400
Westinghouse announced in 2008 that it was working with SNPTC and
Shanghai Nuclear Engineering Research & Design Institute (SNERDI) to
develop jointly a passively safe 1400-1500 MWe design from the
AP1000/CAP1000, for large-scale deployment. SNPTC initially called it
the Large Advanced Passive PWR Nuclear Power Plant (LPP or APWR). It is
one of 16 Key National Projects in China. This development with SNERDI
opens the possibility of China itself exporting the new larger units
with Westinghouse's cooperation.
In December 2009, the State Nuclear Plant Demonstration Company – a
55-45% joint venture company by SNPTC and China Huaneng Group – was set
up to build and operate an initial demonstration unit of the larger
two-loop design, the CAP1400, at Huaneng's Shidaowan site. The new
company signed a set of agreements with SNERDI and the State Nuclear
Power Engineering Company (SNPEC) in November 2010 to proceed with the
project. Basic design of the 4040 MWt (ca.1500 MWe gross) reactor was
completed in 2012, major components are ordered and being manufactured.
It will have 193 fuel assemblies, MOX capability, 50 GWd/t burn-up and
improved steam generators. Seismic rating is 300 gal. Dongfang Electric
is to design and build the turbine generator under contract to SNPTC.
The basic design was approved by the National Energy Administration
(NEA) in January 2014. Site works were complete in April 2014, with
final NNSA approvals in September, following a 17-month review. In
December 2014 SNPTC said it was ready to pour first concrete but awaited
State Council permission, then in April 2015 construction of the
turbine hall started. Westinghouse is providing technical consulting
services to SNPTC for the design. More than 80% of the components will
be indigenous, and contracts for 21 of 29 long lead time components had
been signed by February 2015.
CNNC and SNPTC have talked of export potential, and SNPTC said that
“exploration of the global market” for the CAP1400 would start in
2013, particularly in South America and Asia. In mid-2013 SNPTC quoted
approx. $3000/kW capital cost and 7 c/kWh.
CAP1400 may be followed by a larger, 3-loop CAP1700 design if the
passive cooling system can be scaled to that level. Agreements with
Westinghouse stipulate that SNPTC will own the intellectual property
rights for any derivatives over 1350 MWe. SNPEC is doing the engineering
under a team from SNERDI, the Shandong Electric Power Engineering
Consulting Institute (SEPECI), and the State Nuclear Power Equipment
Manufacturing Company (SNPEMC), which will make the components.
CNP-1000, also CNP-600, CNP-300 (ACP 300, ACP600, ACP1000)
CNNC had been working with Westinghouse and Framatome (now Areva) at
SNERDI since the early 1990s to develop a Chinese standard three-loop
PWR design, the CNP-1000. This is developed from the two-loop Qinshan
CNP-300 unit (scaled up to the two-loop CNP-600 units, also at Qinshan),
with high (60 GWd/t) burn-up, 18-month refueling cycle and 20 more (but
shorter) fuel assemblies than the French-origin M310 units at Daya Bay
and Ling Ao.b
In 1997, the Nuclear Power Institute of China (NPIC) at Chengdu became
involved in the reactor design and, early in 2007, SNERDI was reassigned
to concentrate on the AP1000 programme.
CNNC has been keen to create its own brand of advanced
second-generation reactor with full intellectual property rights, and
wanted to build two initial CNP-1000 plants at Fangjiashan, adjacent to
Qinshan near Shanghai, under the 11th Economic Plan, though the design
probably would not have been ready. In early 2007, the CNP-1000
development was put on hold, though this aborted export plans then for
two CNP-1000 units to Pakistan.
Further CNP-600 units are being built at Qinshan and Changjiang,
Hainan. CNNC says they are free of French intellectual property rights.
CNNC is also developing the design to the ACP600 which it calls a
third-generation design and expected to be built on Hainan or in the
northwest Gansu province and exported.c
It will have double containment, 18-24 month refueling cycle, 121 fuel
assemblies (as CNP-600), digital I&C, and 60-year plant life, but
slightly less power – 605 MWe instead of 650 MWe gross.
In October 2011 CNNC announced that its independently-developed
ACP1000 was entering the engineering design stage, initially for Fuqing
units 5&6, with 1100 MWe nominal power and load-following
capability. It has 177 fuel assemblies 3.66 m long. In May 2013 CNNC
finished a preliminary safety analysis report, and was working on
construction design in order to be ready for construction by the end of
the year. CNNC expected to start building the first in 2014, at Fuqing,
with 85% local content, and the second there in 2015. In April 2013 it
announced an export agreement for an ACP1000, for Pakistan. CNNC asserts
full intellectual property rights for the CNP series of reactors,
which have evolved to the ACP series. However, when the National Energy
Administration ordered a rationalization of CNNC’s and CGN’s 1000 MWe
class designs, the ACP1000 morphed into the Hualong One (see description below)
– though CNNC still describes its version of this as ACP1000. Meanwhile
the IAEA approved the ACP1000 design in its Generic Reactor Safety
Review process in December 2014, though the IAEA points out that this
does not “constitute any kind of design certification”.
Two new 300 MWe CNP-300 PWR units are being built at Chasma in
Pakistan by the China Zhongyuan Engineering Corporation. They are
similar to those already commissioned in 2000 and 2011, and similar to
Qinshan 1 – China's first indigenously-designed (by SNERDI) nuclear
power plant.
CNNC was seeking to sell the CNP-300 to Belarus and in Africa, and these will probably now become ACP300.
ACP100 small modular PWR
A ‘key project’ on the 12th Five-Year Plan is CNNC’s multi-purpose
small modular reactor, the ACP100. Preliminary design was completed in
2014 ready for construction start in 2015 and operation in 2017, but it
awaits NDRC approval. The design is based on the larger ACP (and CNP)
units, or AP1000, has passive safety features and will be installed
underground. Seismic tolerance is 300 Gal. It has 57 fuel assemblies
2.15m tall and integral steam generators (287ºC), so that the whole
steam supply system is produced and shipped a single reactor module. It
has passive cooling for decay heat removal. Its 310 MWt produces about
100 MWe, and power plants comprising two to six of these are envisaged,
with 60-year design life and 24-month refueling. Or each module can
supply 1000 GJ/hr, giving 12,000 m3/day desalination (with
MED). Industrial and district heat uses are also envisaged, as is
floating nuclear power plant (FNPP) application. Capacity up to 150 MWe
is envisaged.
CNNC New Energy Corporation (CNNC-CNEC), a joint venture of CNNC
(51%) and China Guodian Corp, is planning to build two ACP100 units in
Putian county, Zhangzhou city, at the south of Fujian province, near
Xiamen and not far from Fuqing, as a demonstration plant. This will be
the CNY 5 billion ($788 million) phase 1 of a larger project.
Construction time is expected to be 36-40 months, starting 2015 for the
two Putian units. CNNC has applied for NDRC approval. A second proposal
was approved for two further CNNC-CNEC units at Zhangzhou-Gulei, but
this is suspended by local government opposition. In April 2015 CNNC
requested a review of the design by IAEA in its Generic Reactor Safety
Review process, expected to take seven months from July.
The project involves a joint venture of three companies for the pilot
plant: CNNC as owner and operator, the Nuclear Power Institute of China
(NPIC) as the reactor designer and China Nuclear Engineering Group
being responsible for plant construction. CNNC-CNEC signed a second
ACP100 agreement with Hengfeng county, Shangrao city in Jiangxi
province, and a third with Ningdu county, Ganzhou city in Jiangxi
province in July 2013 for another ACP100 project costing CNY 16 billion.
Further inland units are planned in Hunan and Jilin provinces, and CNNC
has signed ACP100 development agreements also with Zhejiang and
Heilongjiang provinces. Export potential is considered high, with full
intellectual property rights. CNNC-CNEC will construct major parts of
the reactors in Bashan, Jilin province.
CAP150 Small modular PWR
This is an integral PWR, with SNPTC provenance, being developed from
the CAP1000 in parallel with CAP1400 by SNERDI, using proven fuel and
core design. It is 450 MWt/ 150 MWe and has 8 integral steam generators
(295°C), and claims “a more simplified system and more safety than
current third generation reactors”. It is pitched for remote electricity
supply and district heating, with three-year refueling and design life
of 80 years. It has both active and passive cooling and in an accident
scenario, no operator intervention required for seven days. Seismic
design basis 300 Gal. In mid 2013 SNPTC quoted approx. $5000/kW capital
cost and 9 c/kWh, so significantly more than the CAP1400.
CAP-FNPP
Another SNERDI project is a reactor for floating nuclear power plant
(FNPP). This is to be 200 MWt and relatively low-temperature (250°C), so
only about 40 MWe with two external steam generators and five-year
refueling. See also entry below re Russian FNPP agreement.
CPR-1000, M310+, ACPR1000
The CPR-1000 is a significantly upgraded version of the 900 MWe-class
French M310 three-loop technology imported for the Daya Bay nuclear
power plant in the 1980s and also built at Ling Ao. Known as the
'improved Chinese PWR' and designated Generation II+, it features
digital instrumentation and control and a design life of 60 years. Its
157 fuel assemblies (4.3 m long) have calculated core melt frequency of
1x10-5 and a release probability an order of magnitude lower than this.
Standard construction time is 52 months, and the claimed unit cost
was under CNY 10,000 (US$ 1600) per kilowatt, though 2013 estimates put
it at about $2300/kW domestically. With a capacity of 1080 MWe gross
(1037 MWe net), Ling Ao Phase II is the first plant to be designated as
the CPR-1000 design. The CPR-1000 was being widely and quickly deployed
for domestic use, with 57 likely to be built, as of end of 2010.
Following the Fukushima accident, numbers will be much lower, and there
will be no further approvals. Six were operating by September 2014, with
16 under construction. Tianwan 5&6 may be the last ones built.
China Guangdong Nuclear Power Corporation (CGN) led the development
of the CPR-1000 and established a nearly complete domestic supply chain.
However, Areva retains intellectual property rights, which constrains
overseas sales since the Chinese would need agreement from Areva on a
case-by-case basis. The six CNNC-built units (Fuqing and Fangjiashan)
are often designated M310+.
CGN refers to later units as CPR-1000+, incorporating design
improvements which bring it close to Generation III standard. The first
of these are Yangjiang 3&4, with some design modifications, followed
by units 5&6 which are more fully transitional to ACPR1000 and are
being called that.
Of more significance was its evolution to the Advanced CPR – ACPR1000 –
with full Chinese intellectual property rights, launched by CGNPC in
November 2011 with some fanfare regarding its safety attributes, which
comply with international requirements. CGN has been in cooperation with
Dongfang Electric, Shanghai Electric, Harbin Electric, China First
Heavy Industries, China Erzhong and other companies since 2009 to
develop the ACPR1000, a three-loop unit with double containment and
core-catcher.
CGN made it available for local build on schedule from 2013 with the
first at Yangjiang, units 5&6, to be followed by Hongyanhe 5&6
and Lufeng 1&2 (now to be AP1000). In September 2012 Fangchenggang
3&4 was identified as the demonstration project, with construction
start at the end of 2014, but meanwhile construction started on
Yangjiang 5&6, which CGN said had evolved to be an ACPR1000 design.
Fangchenggang 3 was to be the reference plant for CGN’s bid to build the
Sinop plant in Turkey. Overnight construction cost is expected to be
$2500/kW.
A further development, ACPR1000+, was envisaged for export, from
2014, but was abandoned with the rationalisation to Hualong One
described below, CGN's version of which is HL1000. It was to have a
60-year life and 300 Gal seismic capability. The conceptual design
gained IAEA approval through its Generic Reactor Safety Review process
in May 2013, though the IAEA points out that this does not “constitute
any kind of design certification”.
In January 2012, CGN with Areva and EdF agreed on a partnership to
develop a Generation III reactor based on the CPR-1000, the ACE1000
(Areva-CGN-EdF1000). Mitsubishi Heavy Industries, already designing the
similar-size Atmea1 with Areva, said it will not be involved. The
ACE1000 concept is reported to be evolutionary, with single but
reinforced containment, active safety systems with three 100% loops (so
can do maintenance on one of them outside outages). No more has been
heard of this plan and it has evidently been overtaken by Hualong One.
ACPR small modular PWRs
Not to be outdone by CNNC in the small modular field, CGN has two
small ACPR designs: an ACPR100 and an ACPR50S, both with passive cooling
for decay heat and 60-year design life. Both have standard type fuel
assemblies and fuel enriched to <5% with burnable poison giving 30
month refueling. The ACPR100 is an integral PWR, 450
MWt, 140 MWe, having 69 fuel assemblies. Reactor pressure vessel is 17m
high and 4.4 m inside diameter, operating at 310°C. It is designed as a
module in larger plant and would be installed underground.
The offshore ACPR50S is 200 MWt, 60 MWe with 37 fuel
assemblies and two loops feeding four external steam generators.
Reactor pressure vessel is 7.4m high and 2.5 m inside diameter,
operating at 310°C. It is designed for mounting on a barge as floating
nuclear power plant (FNPP) or possible submersible. The applications for
these are similar to those for the ACP100, but the timescale is longer
and none is expected on line before 2023.
Hualong One – rationalisation of ACP1000 and ACPR1000+
Since 2011 several rounds of negotiations between CNNC and CGN have
grappled with the task of "merging" the two designs as ordered by the
National Energy Administration (NEA) while allowing for some
differences, with impetus given by the regulator. Both are three-loop
designs based to some extent on the French M310, but the cores are very
different: one (ACP1000) has 177 fuel assemblies 3.66m long, the
ACPR1000 has 157 assemblies 4.3 m long, so physically merging the basic
designs was impractical, and in the event the ACP1000 design prevailed,
though it was less mature. Some features of the ACPR1000 are
incorporated, at least in the CGN version, which it calls HL1000.
The Hualong One thus has 177 fuel assemblies 3.66 m long, 18-24 month
refuelling interval, equilibrium fuel load will be 72 assemblies with
4.45% enriched fuel. It has three coolant loops delivering 3150 MWt,
1150 MWe, double containment and active safety systems with some passive
elements, and a 60-year design life. Average burn-up is 45,000 MWd/tU.
Seismic tolerance is 300 Gal. Instrumentation and control systems will
be from Areva-Siemens, but overall 90% will be indigenous components.
Target cost in China is $2800-3000/kWe, though recent estimates mention
$3500/kW. The CNNC and CGN versions will be very similar but not
identical, they will have slightly different safety systems and each
organisation will maintain much of its own supply chain. The new design
has been variously called Hualong 1000 or HL1000 by CGN, ACP1000 by
CNNC, and generically Hualong One, or HPR1000 – Hualong Pressurised
Reactor.
The first units will be Fangchenggang 3&4 (CGN) and Fuqing
5&6 (CNNC). The 'rationalisation' was helped by greater commonality
in ownership of the two companies as set out in September 2012 though
still not implemented a year later. Fuqing 5 started construction in May
2015.
VVER
Russia's Atomstroyexport was general contractor and equipment
provider for the Tianwan 1&2 AES-91 power plants using the V-428
version of the well-proven VVER-1000 reactor of 1060 MWe capacity. The
reactors incorporate Finnish safety features and Siemens-Areva
instrumentation and control (I&C) systems. Russia's Energoatom is
responsible for maintenance from 2009. Tianwan units 3&4 will use
the same version of the VVER-1000 reactor with Areva I&C systems.
In 2013 Atomergoproekt said it was promoting the VVER-TOI to CNNC and engineering companies.
Russian Floating Nuclear Power Plants
In May 2014 the China Atomic Energy Authority (CAEA) signed an
agreement with Rosatom to cooperate in construction of floating nuclear
cogeneration plants (FNPP) for China offshore islands. These would be
built in China but be based on Russian technology, and possibly using
Russian KLT-40S reactors – Russia’s TVEL anticipates providing fuel for
them. In July 2014 Rusatom Overseas signed a further agreement, this
time with CNNC New Energy, for the joint development of FNPPs – both
barge-mounted and self-propelled – from 2019.
Candu
From 1998 Atomic Energy of Canada Ltd (AECL) built the two-unit
Qinshan Phase III plant on schedule and under budget and estimates that
it could be replicated for 25% lower cost. Any replication would be on
the basis of involving local engineering teams, not on a turnkey basis,
but the technology is now well understood and the decades-old Candu-6
design would likely pose fewer problems for technology transfer than
state-of-the-art third-generation designs from Westinghouse and Areva.
(The Candu-6 units at Wolsong 2-4 in Korea had substantial local
content, reaching 75% localization with unit 4.)
In September 2005, AECL signed a technology development agreement
with CNNC which opened the possibility of it supplying further Candu-6
reactors and undertaking fuel cycle developments based on them. This
agreement with CNNC was passed to its subsidiary, the Nuclear Power
Institute of China (NPIC). From 2008 it has focused on joint development
of the Advanced Fuel Cycle Candu Reactor (AFCR) – see R&D section of China Fuel Cycle paper.
HTR, HTR-200, HTR-600, etc
In February 2006, the State Council announced that the small
high-temperature gas-cooled reactor (HTR) was the second of two high
priority National Major Science & Technology Projects for the next
15 years. This aims at exploring co-generation options in the near-term
and producing hydrogen in the long term.
The small HTR-PM (HTR Pebble-bed Modular) units with pebble bed fuel
and helium coolant were to be 200 MWe reactors, similar to that then
being developed in South Africa, but plans have evolved to make them
twin 105 MWe (equivalent) reactors so that they can retain the same core
configuration as the prototype HTR-10. The twin units, each with a
single steam generator, will drive a single steam turbine. Core height
is 11 metres, and steam will be at 566°C. The engineering of the key
structures, systems, and components is based on Chinese capabilities,
though they include completely new technical features. Thermal
efficiency of 40%, localization 75%, and 50-month construction for the
first unit is envisaged.
China Huaneng Group (CHNG) is the lead organization in the consortium
to build the demonstration Shidaowan HTR-PM with China Nuclear
Engineering & Construction Group (CNEC) and Tsinghua University's
INET, which is the R&D leader. Chinergy Co., a joint venture of
Tsinghua and CNEC, is the main contractor for the nuclear island.
Following the agreement on HTR industrialization cooperation between
CNEC and Tsinghua University in 2003, the two parties signed a further
agreement on commercialization of the HTR in March 2014. CNEC is
responsible for the HTR technical implementation, and becomes the main
investor of HTR commercial promotion at home and abroad.
Thus the initial HTR-PM will pave the way for commercial versions
with multiple modules each 2x105 MWe with its own turbine, hence 400
MWe, 600 MWe or 800 MWe reactor units.* The main promotion is of the 600
MWe version. (It is possible that these commercial HTR plants will have
larger turbines.) Then in April 2015 CNEC announced that its proposal
for two commercial 600 MWe HTRs at Ruijin city in Jiangxi province had
passed an initial feasibility review. This HTR-600 is based on HTR-200
by adding modules. CNEC and the provincial government will apply to NDRC
for approval, and hope to start construction in 2017 for grid
connection in 2021. No major utility has been named yet.
Fast neutron reactor
Longer-term, fast neutron reactors (FNRs) are seen as the main
technology, and CNNC expects the FNR to become predominant by
mid-century. A 65 MWt fast neutron reactor – the Chinese Experimental
Fast Reactor (CEFR) – near Beijing achieved criticality in July 2010,
and was grid-connected a year later.6
Based on this, a 600 MWe pre-conceptual design was developed. The
current plan is to develop an indigenous 1000 MWe design to begin
construction in 2017, and commissioning 2023. This is known as the
Chinese Demonstration Fast Reactor (CDFR) project 1. It is intended to
be followed by a CFR1000 for commercial operation from 2030, according
to China Institute of Atomic Energy. Xiapu in Fujian province is
reported to be a second FNR site.
In addition to CDFR project 1, in October 2009, an agreement with
Russia confirmed earlier indications that China would opt for the BN-800
technology as CDFR project 2. The 880 MWe gross BN-800 reactor which
has been built by OKBM Afrikantov at Beloyarsk in Siberia is the
reference design and the first two in China were planned to start
construction in 2013 at Sanming, Fujian province, with the first to be
in operation in 2019 (see see section below on Sanming).
However, negotiations on price delayed the project and
NIAEP-Atomstroyexport then expected the first contracts to be in place
at the end of 2014, but the project is reported to be suspended
indefinitely.
Embarking upon Generation III plants
In September 2004, the State Council approved plans for two units at
Sanmen, followed by six units at Yangjiang (two to start with), these to
be 1000 or 1500 MWe reactors pioneering Generation III nuclear
technology from overseas. The Sanmen (in Zhejiang province) and
Yangjiang (in Guangdong province) reactors were subject to an open
bidding process for third-generation designs, with contracts to be
awarded in mid-2006 – in the event, mid-2007 – putting them clearly into
the 11th Five Year Plan.
Bidding process
This open bidding process underlined the extent to which China is
making itself part of the world nuclear industry, and yet at first
remaining somewhat ambivalent about that.
Three bids were received for the four Sanmen and Yangjiang reactors:
from Westinghouse (AP1000 reactors), Areva (EPR) and Atomstroyexport
(VVER-1000 model V-392). The State Nuclear Power Technology Corporation
(SNPTC), directly under China's State Council, was in charge of
technology selection for new plants being bid from overseas.
Some 200 experts spent over a year evaluating Generation III designs
and in September 2006 most of the 34 assigned to decide voted for the
AP1000. The key factors in choosing this were passive design, simplified
safety system, modular construction giving more rapid build and better
cost control, and smaller components allowing more ready localization.
The USA, French and Russian governments were reported to be giving
firm support as finance and support arrangements were put in place. The
US Export-Import bank approved $5 billion in loan guarantees for the
Westinghouse bid, and the French Coface company was expected similarly
to finance Areva for its bid. The US Nuclear Regulatory Commission gave
approval for Westinghouse to export equipment and engineering services
as well as the initial fuel load and one replacement for the four units.
Bids for both two-unit plants were received in Beijing on behalf of the
two customers: China General Nuclear Power Co (CGN) for Yangjiang, and
China National Nuclear Corporation (CNNC) for Sanmen. Bids were for the
nuclear portion of each plant only, the turbine tenders to be called for
subsequently.
Bids were assessed on level of technology, the degree to which it was
proven, price, local content, and technology transfer – which
apparently became the major factor. Areva and Westinghouse were
short-listed. However, the decision on reactor type was delayed, and
came under review at the highest political level, with CNNC evidently
pushing for the use of indigenous second-generation designs for both
sites.
In December 2006, 22 months after the bids were submitted and after
several revisions to them, the Westinghouse AP1000 reactor design was
confirmed for the four units – two each at Sanmen and Yangjiang. Early
in 2007, the two units planned for the Yangjiang site were switched to
Haiyang in the more northerly Shandong province, making way for two EPR
units Areva was in negotiations to build at Yangjiang. Later in 2007,
plans for the EPRs under consideration for Yangjiang were transferred to
another Guangdong site – Taishan – since there was pressure to build a
lot of capacity quickly at Yangjiang.
Sanmen 1&2 and Haiyang 1&2
A framework agreement was signed at the end of February 2007 between
Westinghouse and SNPTC specifying Haiyang and Sanmen for the four AP1000
units. In July 2007, Westinghouse, along with consortium partner Shaw,
signed the contracts with SNPTC, Sanmen Nuclear Power Company (51% owned
by CNNC), Shangdong Nuclear Power Company (61% owned by CPI) and China
National Technical Import & Export Corporation (CNTIC) for four
AP1000 reactors. Specific terms were not disclosed but the figure of
$5.3 billion for the first two was widely quoted. In December 2007 the
Chinese and US governments signed the intergovernmental agreement for
the construction of AP1000 projects in China and technology transfer.
Sanmen site works commenced in February 2008 and full construction on
Sanmen 1 – the world's first AP1000 unit – officially commenced on 19
April 2009. The reactor was expected to begin operation at the end of
2015 with the second less than one year later. First concrete at Haiyang
1 was in September 2009, and the pressure vessel was installed in
January 2012. The Haiyang units are expected to commence operation in
2016. Construction has been slower than planned, the main problem being
with US-made main coolant pumps (four in each reactor). These worked
well in normal operation but had insufficient inertia to continue long
enough for full passive safety effectiveness when not powered. Following
successful tests, the modified pumps are being shipped from
Curtis-Wright to Sanmen in October 2015.
AP1000 construction and equipment contracts
Westinghouse and Shaw Group have an engineering, procurement,
commissioning and start-up as well as project management contract with
SNPTC for the first four reactors (Sanmen & Haiyang). Also Shaw has a
contract with State Nuclear Power Engineering Corp. Ltd, a SNPTC
subsidiary, for technical support for the first two Dafan, Xianning
units in Hubei province, including engineering and design management,
project controls, quality assurance, construction management and project
management.
In April 2007, Westinghouse signed a $350 million contract with
Doosan Heavy Industries in Korea for two pressure vessels and four steam
generators for Sanmen 1 and Haiyang 1. The pressure vessels for the
other two units are being made by Chinese manufacturers: China First
Heavy Industries (CFHI, also known as YiZhong) for Sanmen 2 and Shanghai
Electric Group Corporation (SEC) for Haiyang 2. Steam generators for
Sanmen 2 and Haiyang 2 were manufactured by Harbin Power Equipment Co.,
Ltd. (HPEC, now Harbin Electric Co, HEC) and SEC, respectively, though a
contract for Sanmen 2 steam generators was let to Spain's ENSA in 2011.
The Sanmen 1 reactor pressure vessel arrived on site from Doosan in
July 2011.
All four steam turbine generators were supplied by Mitsubishi Heavy
Industries (MHI). In a $521 million deal, Sanmen Nuclear Power ordered
two turbine generator packages from MHI at the end of September 2007,
with Shandong Nuclear Power ordering another two early in 2008. MHI's
Takasago Machinery Works manufactured the turbines, including rotors and
blades. Mitsubishi Electric Corporation is supplying the generators and
Harbin Electric Co (HEC), partnering with MHI, was responsible for
turbine casings, piping and associated facilities. The turbines boost
the capacity of the reactors from their original 1175 MWe to 1250 MWe
gross.
In 2014 Westinghouse said that the second plant at each site saw a
30% reduction in manpower requirements compared with the first unit. The
company is also working on the next eight units in China and expects
about a 50% productivity increase compared with the first two Chinese
AP1000 units.
The AP1000 Technology Transfer agreement to SNPTC covered 34 task
packages in 7 categories, and in 2011 the process was still under way,
with 78% of the documentation done by August. Some 27 sublicence
agreements involved 30 entities.
In November 2010, further contracts were signed between SNPTC and
Westinghouse, including one for Westinghouse to provide SNPTC with
technical consulting services in research and development of the CAP1400
nuclear power plant, to be developed by SNPTC with Chinese intellectual
property rights. Westinghouse said that having shared design technology
with SNERDI, it expected 100% localization by 2015.
In January 2011, a further agreement was signed with SNPTC to deploy
further AP1000 units, and to extend the 2008 technology cooperation
agreement for another two years. SNPTC said the deal also included
measures "to develop cooperation in the field of overseas markets."
Another agreement was signed with China Baotou Nuclear Fuel Co "to
design, manufacture and install fuel fabrication equipment that will
enable China to manufacture fuel" for AP1000 units. The latter $35
million contract involves supply and installation of US equipment at
Baotou.
In June 2011 Westinghouse confirmed that as part of the earlier
construction agreement it would transfer intellectual property rights to
SNPTC. In September 2014 Westinghouse said that it expected to be
involved in orders for eight further units, followed by 12 more inland
and 12 on the coast. It expected “to have 20 AP1000 units under
construction in the next five years in China.”
In 2015 SNPTC merged with CPI and took over all its nuclear business
as a sub-group of the new State Power Investment Corporation (SPI)
entity. It then claimed that its supply chain could support
construction of 6-8 AP/CAP units each year, with up to five suppliers
for each key item.
Taishan 1&2 EPR
In February 2007, EDF entered a cooperation agreement with CGN (then:
CGNPC) to build and operate a two-unit EPR power station at Yangjiang
in Guangdong province. This deal was not expected to involve the
technology transfer which is central to the Westinghouse contracts,
since the EPR has multiple redundant safety systems rather than passive
safety systems and is seen to be more complex and expensive, hence of
less long-term interest to China. However, negotiations with Areva and
EDF dragged on and in August 2007 it was announced that the EPR project
had been shuffled to Taishan (in Guangdong) so that six CPR-1000 units
previously planned for that site could be built at Yangjiang as soon as
possible.
At a November 2007 ceremony attended by Chinese president Hu Jintao
and French president Nicolas Sarkozy in Beijing's Great Hall of the
People, Areva initialed an €8 billion contract with CGN for the two EPRs
at Taishan plus supply of fuel to 2026 and other materials and services
for them. The whole project, including fuel supply, totals €8 billion,
of which the nuclear reactors themselves were reported to be about €3.5
billion. Steam turbine generators costing €300 million are included in
the larger sum. The Guangdong Development Commission quoted the total
investment in both units as CNY 49.85 billion ($7.3 billion). The joint
venture partners will put up CNY 16.45 billion and the balance will be
borrowed with guarantee from the Central Bank of France. French export
credits for the project are reported as €1.7 billion ($2.4 billion),
covering purchase of equipment such as steam generators for unit 1 from
French suppliers.
In August 2008, EDF and CGN signed the final agreements for the
creation of Guangdong Taishan Nuclear Power Joint Venture Company
Limited (TNPC). EDF will hold 30% of TNPC for a period of 50 years (the
maximum period permitted for a joint venture in China), CGN 70%. TNPC
will oversee the building, then own and operate the plant. EDF is paying
€600 to 800 million over four years for this share, subject to approval
by the National Development and Reform Commission (NDRC) and the
Ministry of Commerce. (EDF is project manager and architect for the
Flamanville 3 EPR project in France, and this initiative consolidates
its change in corporate strategy outside France.)
CGN authorised construction at Taishan in July 2008 and first
concrete was poured in October 2009, though the official inauguration
ceremony was not until 21 December. The first unit was expected to be
connected to the grid early in 2014 with commercial operation two months
later, and the second was to be completed in 2015, but they are at
least two years behind. The major components for unit 1 are imported:
the pressure vessel from Mitsubishi Heavy Industries (MHI) in Japan and
the steam generators from Areva Chalon/St. Marcel in France, but those
for unit 2 are all built in China: the pressure vessel by Dongfang
Electric (DEC), the steam generators by DEC (two) and Shanghai Electric
(two). The Arabelle steam turbines and 1750 MWe generators are being
purchased separately from Alstom and Dongfang Electric Co respectively.
The first generator was shipped by DEC in August 2013. In March 2012
Areva said unit 1 was 69% complete, with reactor pressure vessel
delivered.
In April 2013 Areva, EDF and CGN signed a tripartite agreement for
“deeper industrial and commercial cooperation” in building new nuclear
power plants and improving all CGN units. However, as of 2013 it appears
that not more than two further EPR units will be built in China.
Indigenous Generation III plants
Late in 2012 the National Energy Administration (NEA), reflecting
State Council views, made it clear that indigenous reactor designs
needed to be progressed to Generation III safety standards. See comments
above on ACP1000, ACPR1000 and Hualong One.
Nuclear growth
The first two nuclear power plants in mainland China were at Daya Bay
near Hong Kong and Qinshan, south of Shanghai, with construction
starting in the mid-1980s. Localisation has risen from 1% at Daya Bay to
64% at Ling Ao and 85% at Yangjiang.
China's concerted nuclear expansion began with the National
Development and Reform Commission's (NDRC's) Tenth Economic Plan for the
years 2001-2005, with increased self-reliance. (China's first economic
plan was in 1953 and began China's centrally planned industrialization
under Mao Zedong.) It incorporated the construction of eight nuclear
power plants, though the timeline for contracts was extended, putting
the last two projects into the 11th plan. The Eleventh Economic Plan for
the years 2006-2010 set even more ambitious goals than the Tenth for
new nuclear plant construction, and marked a watershed in China's
commitment to third-generation reactors, such as the Sanmen plant in
Zhejiang province and Haiyang plant in Shandong province (see section
above on Reactor technology)
as well as maturing of CPR-1000 technology. The 11th Five-Year Plan
(2006-10) also had firmer environmental goals than previously, including
reduction of 20% in the amount of energy required per unit of GDP, i.e. 4% reduction per year.
In 2007, it was announced that three state-owned corporations had
been approved by NNSA to own and operate nuclear power plants: CNNC, CGN
and China Power Investment Corporation (CPI). Any other public or
private companies are to have minority shares in new projects, which is
proving a severe constraint on the ambitions of the country's main power
utilities (including Huaneng, Huadian, Datang and Guodian), all of
which have set up nuclear subsidiaries or become involved in nuclear
projects. CGN is increasingly preeminent in actual nuclear power plants.
The 12th Five-Year Plan (2011-15) included construction start on
phase II of Tianwan, Hongyanhe, Sanmen and Haiyang, as well as phase I
of inland sites: Taohuajiang, Xianning, and Pengze (2 reactors each
except Taohuajiang: 4). By the end of the 12th Five Year Plan some 25
GWe of new capacity was planned to be operational, making some 40 GWe,
and 45 GWe more might be added by the end of the 13th Five Year Plan.
The 12th Five-year science & technology plan released in July 2011
called for building a demonstration CAP-1400 plant for grid connection
in 2015 and the demonstration HTR-PM to begin test operation at
Shidaowan before 2015. Construction starts were delayed following the
Fukushima accident, and all the inland plants were put on hold.
More than 16 provinces, regions and municipalities announced
intentions to build nuclear power plants in the 12th Five Year Plan
2011-15. so that nuclear plants were operating or under construction in
all coastal provinces except Hebei. Provinces put together firm
proposals by 2008 and submitted them to the central government's
National Development and Reform Commission (NDRC) for approval during
2009. NRDC consideration is via the new National Energy Administration
(NEA). A great many proposals were received, many of which will be
deferred to the 13th Plan.
The approvals process in China has three stages:
- Siting and feasibility study, with project approval from NDRC.
- Construction, requiring first a construction permit and later a fuel loading permit from NNSA.
- Commissioning, leading to NNSA operating permit.
In 2014 CPI had plans to achieve 14 GWe of operational capacity by
2020, with 10 GWe under construction then, at nine sites with 40 units.
All of this except phase I of Hongyanhe (4xCPR-1000) would be AP1000.
The complex ownership structure of Chinese nuclear plants is
described in Appendix 1: Government Structure and Ownership, and China's
considerable heavy engineering and manufacturing capacity is detailed
in the information page on Heavy Manufacturing of Power Plants. The capacity at the end of 2013 was for eight sets of reactor equipment per year – over 8000 MWe.
On the people and skills front, 47 colleges and research institutes
have nuclear major, and more than 2000 graduate each year (4000 in 10th
Five-Year Plan, 11,000 in 11th Five-Year Plan).
Nuclear technology exports
China has a determined policy at NDRC level of exporting nuclear
technology, based on development of the CAP1400 reactor with Chinese
intellectual property rights and backed by full fuel cycle capability.
The policy is being pursued at a high level politically, utilising
China's economic and diplomatic influence. CNNC and SNPTC are focused on
the export potential of the CAP1400, and SNPTC aims at “exploration of
the global market” from 2013, particularly in South America and Asia. In
January 2015 the cabinet announced new incentives and financing for
industry exports, particularly nuclear power and railways, on the back
of $103 billion outbound trade and investment in 2014.
Export sales and prospects for Chinese nuclear power plants
Country |
Plant |
Type |
Est. cost |
Company |
Status, financing |
Pakistan |
Chasma 3&4 |
CNP-300 |
$2.37 billion |
CNNC |
Under construction, Chinese finance 82% of $1.9 billion |
|
Karachi Coastal |
Hualong One |
$9.6 billion |
CNNC |
Planned, $6.5 billion vendor finance, maybe 82% China finance |
Romania |
Cernavoda 3&4 |
Candu 6 |
€6.5 billion |
CGN |
Planned, Chinese finance |
Argentina |
Atucha 3 |
Candu 6 |
|
CNNC |
Planned, with local involvement and $2 billion Chinese financing |
|
Atucha 4 or other site |
Hualong One |
|
CNNC |
Vendor financing envisaged |
UK |
Bradwell |
Hualong One |
|
CNNC/CGN |
|
Turkey |
? |
AP1000 or CAP1400 |
|
SNPTC |
Exclusive negotiations involving Westinghouse |
South Africa |
|
CAP1400 |
|
SNPTC |
Prepare for submitting bid |
|
|
HTR600 |
|
CNEC |
|
In Pakistan, two new 300 MWe CNP-300 PWR units are being built at
Chasma, joining the two built there earlier. In 2013 CNNC announced an
export agreement for twin ACP1000 units, for Pakistan’s Karachi Coastal
Power station, costing $9.6 billion. This will now use Hualong One
technology.
In May 2014 Romania’s Nuclearelectrica signed an agreement with CGN
to explore the prospect of building two new reactors at Cernavoda, which
currently has two Candu 6 reactors. In November 2013 two nuclear
cooperation agreements were signed by Nuclearlectrica with CGN, one a
letter of intent relating to construction of units 3&4.
In July 2014 a high-level agreement was signed by Argentine and
Chinese presidents towards construction of Atucha 3 as a PHWR unit. CNNC
will provide most of the equipment and technical services under
long-term financing. Candu Energy will be a subcontractor to CNNC. In
September the utility NASA signed a commercial framework contract with
CNNC to progress this, with CNNC’s Qinshan Phase III units as reference
design for a Candu 6 unit. It will have $3.8 billion in local input and
$2 billion from China and elsewhere under a long-term financing
arrangement.
SNPTC is keen to export the CAP1400 reactor, and considers Turkey and
South Africa to be good prospects. In November 2014 SNPTC signed an
agreement with Turkey’s utility EUAS and Westinghouse to begin exclusive
negotiations to develop and construct a four-unit nuclear power plant
in Turkey. In December 2014 it signed two agreements in South Africa
with a view to nuclear power plant construction, and CNNC signed another
there.
CNEC has promoted the HTR technology to Dubai, UAE, Saudi Arabia,
South Africa and Indonesia, and has signed agreements with some of them.
As well as specifically nuclear exports, the State Grid Corporation
of China (SGCC) is building a 2084 km UHV DC transmission line in
Brazil, for over $2.3 billion.
Operating nuclear plants: varied beginnings to 2010
Daya Bay, Ling Ao Phase I
These are essentially on the one site in Guangdong province, close to
Hong Kong. The Daya Bay reactors are standard 3-loop French PWR units
supplied by Framatome and designated M310, with GEC-Alstom turbines.
Electricite de France (EDF) managed construction, starting August 1987,
with the participation of Chinese engineers. Commercial operation of the
two Daya Bay units was in February and May 1994. There were long
outages in 1994-96 when Framatome had to replace major components.
Reactor vessel heads were replaced in 2004. The plant produces about 13
billion kWh per year, with 70% transmitted to Hong Kong and 30% to Guangdong.
The Ling Ao Phase I reactors are virtually replicas of adjacent Daya
Bay units. Construction started in May 1997 and Ling Ao 1 started up in
February 2002 entering commercial operation in May. Ling Ao 2 was
connected to the grid about September 2002 and entered commercial
operation in January 2003. The two Ling Ao reactors use French M310
technology supplied by Framatome (now Areva), but with 30% localisation.
They are reported to have cost $1800 per kilowatt.
Daya Bay and Ling Ao I & II together comprise the 'Daya Bay
nuclear power base' managed by Daya Bay Nuclear Power Operations &
Management Co (DNMC), part of China General Nuclear Power Group (CGN).
For Ling Ao Phase II, see below.
Qinshan
Qinshan 1 in Zhejiang province 100 km southwest of Shanghai, is
China's first indigenously-designed and constructed nuclear power plant
(though with the pressure vessel supplied by Mitsubishi, Japan). Design
of the 300 MWe PWR was by the Shanghai Nuclear Engineering Research
& Design Institute (SNERDI). Construction work spanned 6.5 years
from March 1985, with first grid connection in December 1991. It was
shut down for 14 months for major repairs from mid-1998.
In October 2007, Qinshan 1 was shut down for a major upgrade. The
entire instrumentation and control system was replaced, along with the
reactor pressure vessel head and control rod drives. Areva NP supervised
the work, which is likely to lead to life extension beyond the original
30 years.
Qinshan Phase II units 1&2 are locally-designed and constructed
2-loop PWR reactors, scaled up from Qinshan 1, and designated CNP-600.
Local content was 55%. Unit 1 started up at the end of 2001 and entered
commercial operation in April 2002. Unit 2 started up in March 2004,
with commercial operation in May 2004. Units 3 & 4 are similar, with
local content of 77%. After 53 months construction, unit 3 was grid
connected on 1 August 2010, and entered commercial operation 12 weeks
later8.
Unit 4 was grid-connected in November 2011 and entered commercial
operation in April 2012. CNNC claims that Qinshan phase II "is the first
independently-designed, built, managed and operated large commercial
nuclear power station in China."
Construction of the second stage of Qinshan Phase II was formally
inaugurated at the end of April 2006, though first concrete had been
poured for unit 3 in March. That for unit 4 was poured in January 2007.
Local content of the two 650 MWe CNP-600 reactors is more than 70% and
they entered commercial operation in 2010 and 2012.
In 2004, CNNC announced that the next two Qinshan units would be 1000
MWe indigenous units (in effect Fangjiashan, adjacent to Qinshan 1, has
taken over this role).
Qinshan Phase III units 1&2 use the Candu 6 pressurised heavy
water reactor (PHWR) technology, with Atomic Energy of Canada (AECL)
being the main contractor of the project on a turnkey basis.
Construction began in 1997 and unit 1 started up in September 2002 and
unit 2 in April 2003. They are each about 678 MWe net.
Tianwan phase I
Tianwan Phase I at Lianyungang city in Jiangsu province is a Russian
AES-91 power plant (with two 1060 MWe V-428 VVER reactors) constructed
under a cooperation agreement between China and Russia – the largest
such project ever. The cost is reported to be $3.2 billion, with China
contributing $1.8 billion of this. Completion was delayed due to
corrosion in the steam generators which resulted in some tubes having to
be plugged with a net loss of capacity of about 2%. The first unit was
grid connected in May 2006 and put into commercial operation in June
2007. The second was grid connected in May 2007, with commercial
operation in August 2007. Design life is 40 years.
Ling Ao Phase II
While the bidding process for the delayed Generation III plants from
overseas vendors was in train over more than two years (see section
above on Embarking upon Generation III plants),
the China General Nuclear Power Group (CGN) signed contracts with
Chinese designers and manufacturers for two reactors as Phase II of the
Ling Ao power station (also known as Ling Dong). Construction started in
December 2005 with the 1080 MWe (gross), 1037 MWe (net) units. They are
transitional M310 - CPR-1000 units of 1037 MWe net. Unit 1 is about 50%
localized and unit 2 is 70% localized, built under the project
management of China Nuclear Power Engineering Corporation (CNPEC), part
of CGNPC. Low-speed Arabelle turbine-generator sets were provided by
Alstom. In June 2009, the first Chinese-made reactor pressure vessel for
a 1000 MWe class reactor was delivered for unit 2, from Dongfang
(Guangzhou) Heavy Machinery Co. Unit 1 started up in June 2010 with grid
connection in mid-July, 54 months after construction start, and entered
commercial operation in September. Unit 2 is expected to commence
operation in 2011. Unit 2 was grid connected in May, 60 months after
construction start, and commenced commercial operation on schedule in
August 2011. The plant is managed by Daya Bay Nuclear Power Operations
& Management Co (DNMC).
Operating nuclear reactors
Units |
Province |
Net capacity (each) |
Type |
Operator |
Commercial operation |
Daya Bay 1&2 |
Guangdong |
944 MWe |
French M310 |
CGN |
1994 |
Qinshan Phase I |
Zhejiang |
298 MWe |
CNP-300 |
CNNC |
April 1994 |
Qinshan Phase II, 1&2 |
Zhejiang |
610 MWe |
CNP-600 |
CNNC |
2002, 2004 |
Qinshan Phase II, 3&4 |
Zhejiang |
620 MWe |
CNP-600 |
CNNC |
2010, 2012 |
Qinshan Phase III, 1&2 |
Zhejiang |
678 MWe |
Candu 6 PHWR |
CNNC |
2002, 2003 |
Fangjiashan 1&2 |
Zhejiang |
1020 MWe |
CPR-1000 (M310+) |
CNNC |
Dec 2014, Feb 2015 |
Ling Ao Phase I, 1&2 |
Guangdong |
938 MWe |
French M310 |
CGN |
2002, 2003 |
Ling Ao Phase II, 1&2 |
Guangdong |
1026 MWe |
CPR-1000 (M310) |
CGN |
Sept 2010, Aug 2011 |
Tianwan 1&2 |
Jiangsu |
990 MWe |
VVER-1000 |
CNNC |
2007, 2007 |
Ningde 1&2 |
Fujian |
1020 MWe |
CPR-1000 |
CGN & Datang |
April 2013, May 2014 |
Ningde 3 |
Fujian |
1020 MWe |
CPR-1000 |
CGN & Datang |
June 2015 |
Hongyanhe 1&2 |
Liaoning |
1024 MWe |
CPR-1000 |
CGN & SPI |
June 2013, May 2014 |
Hongyanhe 3 |
Liaoning |
1020 MWe |
CPR-1000 |
CGN & SPI |
Aug 2015 |
Yangjiang 1&2 |
Guangdong |
1021 MWe |
CPR-1000 |
CGN |
March 2014, June 2015 |
Fuqing 1&2 |
Fujian |
1020 MWe |
CPR-1000 (M310+) |
CNNC & Huadian |
Nov 2014, (late 2015) |
Total: 27 | | 24,196 MWe | |
Nuclear plants under construction and planned
China General Nuclear Power (CGN) expected to spend $ 9.5 billion on
its Ling Ao Phase II, Yangjiang and Taishan nuclear power plants by 2010
and to have 6000 MWe on line by then, with 12,000 MWe under
construction. Work is under way at all these sites and others. It also
planned to start on the Lufeng plant in Guangdong and Wuhu in Anhui
province, but awaited NDRC approval. It is expecting to have 34,000 MWe
nuclear capacity on line by 2020, providing 20% of the province's power,
and 16,000 MWe under construction then. From 2010 it expected to
commission three units per year and, from 2015, four units per year. CGN
is also, due to State Council policy, committed to developing
significant wind capacity through CGN Wind Co. It projects a total of
500 MWe by 2020.
China Nuclear Power Plant Construction
Jesper Antonsson (data from PRIS) 2015. Red = estimated completion.
In 2006, China National Nuclear Corporation (CNNC) signed agreements
in Liaoning, Hebei, Shandong and Hunan provinces and six cities in
Hunan, Anhui and Guangdong provinces to develop nuclear projects. CNNC
has pointed out that there is room for 30 GWe of further capacity by
2020 in coastal areas and maybe more inland such as Hunan "where
conditions permit". In October 2007, CNNC's list of projects included
Chuanshan (Jiangsu province), Jiyang (Anhui), Hebao Island (Guangdong),
Shizu (Chongqing), Xudabao/ Xudapu (Liaoning) and Qiaofushan (Hebei)
amongst others.
Since then, announcements from CNNC, CGN and others are reported in
the individual reactor reports in the second half of this paper.
Nuclear reactors under construction and planned
Plant |
Province |
MWe gross |
Reactor model |
Project control |
Construction start |
Operation, grid connect |
Hongyanhe unit 4 |
Liaoning |
1119 |
CPR-1000 |
CGN, with SPI |
8/09 |
late 2015 |
Ningde unit 4 |
Fujian |
1089 |
CPR-1000 |
CGN, with Datang |
9/10 |
early 2016 |
Yangjiang 3&4 |
Guangdong |
2x1089 |
CPR-1000+ |
CGN |
11/10, 11/12 |
late 2015, 2017 |
Sanmen units 1&2 |
Zhejiang |
2x1250 |
AP1000 |
CNNC |
3/09, 12/09 |
2016, 2017 |
Haiyang units 1&2 |
Shandong |
2x1250 |
AP1000 |
SPI |
9/09, 6/10 |
12/2015, 3/16 |
Taishan units 1&2 |
Guangdong |
2x1750 |
EPR |
CGN |
10/09, 4/10 |
early 2016, late 2016 |
Shandong Shidaowan |
Shandong |
210 |
HTR-PM |
Huaneng |
12/12 |
2017 |
Fangchenggang units 1&2 |
Guangxi |
2x1080 |
CPR-1000 |
CGN |
7/10, 2011 |
2015, 2016 |
Changjiang units 1&2 |
Hainan |
2x650 |
CNP-600 |
CNNC & Huaneng |
4/10, 11/10 |
2015, 12/2015 |
Fuqing units 3&4 |
Fujian |
2x1080 |
CPR-1000 (M310+) |
CNNC & Huadian |
12/10, 11/12 |
late 2015, 2017 |
Tianwan units 3&4 |
Jiangsu |
2x1060 |
VVER-1000 V-428M |
CNNC |
12/12, 9/13 |
2/2016, 3/2017 |
Yangjiang units 5&6 |
Guangdong |
2x1080 |
ACPR1000 |
CGN |
9/13, 12/13 |
2018, 2019 |
Hongyanhe units 5&6 |
Liaoning |
2x1080 |
ACPR1000 |
CGN, with SPI |
3/15, 7/15 |
11/2019, 8/2020 |
Shidaowan units 1&2 |
Shandong |
2x1400 |
CAP1400 |
SNPTC & Huaneng |
5/15, 8/15 |
12/2019, 2020 |
Fuqing units 5&6 |
Fujian |
2x1150 |
Hualong 1 |
CNNC & Huadian |
5/15, 2015* |
2019, 2020 |
Fangchenggang units 3&4 |
Guangxi |
2x1150 |
Hualong 1 |
CGN |
late 2015, 2016* |
2020, 2021 |
Ningde units 5&6 |
Fujian |
2x1150 |
Hualong 1 |
CGN & Datang |
early 2016, 2017* |
2021, 2022 |
Xudabao/Xudapu units 1&2 |
Liaoning |
2x1250 |
AP1000 |
CNNC, Datang |
2015-16* |
2019, 2020 |
Sanmen units 3&4 |
Zhejiang |
2x1250 |
AP1000 |
CNNC |
2015-16* |
|
Haiyang units 3&4 |
Shandong |
2x1250 |
AP1000 |
SPI |
2015-16* |
|
Lufeng (Shanwei) units 1&2 |
Guangdong |
2x1250 |
AP1000 |
CGN |
2015-16* |
2019, 2020 |
Fangchenggang units 5&6 |
Guangxi |
2x1250 |
AP1000 |
CGN |
2015-17 |
|
Bailong units 1&2 |
Guangxi |
2x1250 |
AP1000 |
SPI |
2015-17 |
|
Huizhou units 1&2 |
Guangdong |
2x1250 |
AP1000 |
CGN |
2015-18 |
|
Putian, Zhangzhou units 1&2 |
Fujian |
2x100 |
ACP100 |
CNNC & Guodian |
2015 |
2017 |
Tianwan units 5&6 |
Jiangsu |
2x1080 |
ACPR1000 |
CNNC |
11/15, 2017 |
|
Taishan units 3&4 |
Guangdong |
2x1750 |
EPR? |
CGN |
2015-18 |
|
Changjiang units 3&4 |
Hainan |
2x650 |
CNP-650 or ACP-600 |
CNNC & Huaneng |
2015-18 |
|
Zhangzhou units 1-4 |
Fujian |
4x1250 |
AP1000 |
Guodian & CNNC |
2016 |
|
Sanming units 1&2 |
Fujian |
2x880 |
BN-800? |
CNNC |
? |
2025? |
Taohuajiang units 1-4 |
Hunan (inland) |
4x1250 |
AP1000 |
CNNC |
2016 -18* |
|
Pengze units 1&2 |
Jiangxi (inland) |
2x1250 |
AP1000 |
SPI |
2016-17* |
|
Xianning (Dafan) units 1&2 |
Hubei (inland) |
2x1250 |
AP1000 |
CGN |
2016-17* |
|
|
Under construction |
1x1119 3x1089 1x210 4x1250 1x1150 2x1750 8x1080 2x650 2x1060 =26,306 |
|
|
Planned: |
2x1080 5x1150 26x1250 2x1750 2x1400 2x880 2x650 2x100 =49,970 |
|
Total: 67 | 24 Under const 35 + 8 Planned | 26,306 49,970 |
|
Further nuclear power units proposed
Plant |
Province |
MWe gross |
Expected model |
Project control |
Construction |
Start up |
Nanchong (Nanchun, Sanba) units 1-4 |
Sichuan |
4x1150 |
Hualong 1 |
CGN |
|
|
Shidaowan units 3&4 |
Shandong |
2x1250 |
AP1000 |
SNPTC & Huaneng |
|
|
Tianwan units 7&8 |
Jiangsu |
2x1200 |
VVER-1200 (AES-2006) |
CNNC |
|
|
Xianning (Dafan) units 3&4 |
Hubei |
2x1250 |
AP1000 |
CGN |
|
|
Pengze units 3&4 |
Jiangxi |
2x1250 |
AP1000 |
CPI |
|
|
Bailong units 3&4 |
Guanxi |
2x1250 |
AP1000 |
CPI |
|
|
Shidaowan units 5&6 |
Shandong |
2x1250 |
AP1000 |
SNPTC & Huaneng |
|
|
Ruijin units 1&2 |
Jiangxi |
2x600 (6x210) |
HTR-600 |
CNEC |
2017 |
2022 |
Haiyang units 5&6 |
Shandong |
2x1250 |
AP1000 |
CPI |
|
|
Hongshiding (Rushan) units 1&2 |
Shandong |
2x1150 |
Hualong 1 |
CNNC |
|
|
Cangzhou units 1&2 |
Hebai |
2x1150 |
Hualong 1 |
CNNC & Huadian |
|
|
Xiaomoshan units 3&4 |
Hunan |
2x1250 |
AP1000 |
CPI |
|
|
Pingnan/Baisha units 1&2 |
Guangxi |
2x1250 |
AP1000 |
CPI |
|
|
Pingnan/Baisha units 3&4 |
Guangxi |
2x1250 |
AP1000 |
CPI |
|
|
Xudabao/Xudapu units 3-6 |
Liaoning |
4x1250 |
AP1000 |
CNNC with Datang |
|
|
Lufeng (Shanwei) units 3-6 |
Guangdong |
4x1250? |
AP1000? |
CGN |
|
|
Yingtan units 1-4 |
Jiangxi |
4x1250 |
AP1000 |
Huaneng |
|
|
Nanyang units 1-6 |
Henan |
6x1250? |
AP1000 (if CPI) |
CNNC (or CPI) |
|
|
Xinyang units 1-4 |
Henan |
4x1150 |
Hualong 1 |
CGN |
|
|
Changde (Chenzhou, Hengyang) |
Hunan |
4x1150 |
Hualong 1 |
CNNC & Guodian?, CGN |
|
|
Zhangzhou units 5&6 |
Fujian |
2x1250 |
AP1000 |
CNNC & Guodian |
|
|
Jiyang/Chizhou units 1&2 |
Anhui |
2x1250? |
AP1000 |
CNNC |
|
|
Sanmen units 5&6 |
Zhejiang |
2x1250 |
AP1000 |
CNNC |
|
|
Cangnan units 1&2 |
Zhejiang |
2x1250 |
AP1000 |
CGN & Huaneng |
|
|
Fuling units 1&2 |
Chongqing |
2x1250 |
AP1000 |
CPI |
|
|
Jingyu units 1&2 |
Jilin |
2x1250 |
AP1000 |
CPI & Guodian |
|
|
Donggang units 1&2 |
Liaoning |
2x1150 |
Hualong 1? |
Huadian |
|
|
Xiapu units 1-6 |
Fujian |
6x1250 |
AP1000 |
Huaneng |
|
|
Wuhu units 1&2 |
Anhui |
2x1250 |
AP1000 |
CGN |
|
|
Ningdu units 1&2 |
Jiangxi |
2x100 |
ACP100 |
CNNC & Guodian |
|
|
Xiaomoshan units 1&2 |
Hunan |
2x1250 |
AP1000 |
CPI |
|
|
Yanjiashan/ Wanan/Ji'an units 1&2 |
Jiangxi |
2x1250 |
AP1000 |
CNNC |
|
|
Shaoguan units 1-4 |
Guangdong (inland) |
4x1250 |
AP1000 |
CGN |
|
|
Subtotal: 92 units |
|
64x1250 18x1150 2x1200 6x200 2x100 =104,500 MWe |
|
Further proposals (less definite or further away) |
Cangzhou units 3-6 |
Hebai |
4x1250 |
AP1000 |
CNNC & Huadian |
|
|
Jiyang/Chizhou units 3&4 |
Anhui |
2x1250? |
AP1000? |
CNNC |
|
|
Cangnan units 3-6 |
Zhejiang |
4x1250 |
AP1000 |
CGN/Huaneng |
|
|
Longyou/Zhexi units 1-4 |
Zhejiang |
4x1250 |
AP1000 |
CNNC |
|
|
Haijia/Haifeng units 1&2 |
Guangdong |
2x1250 |
AP1000 |
CGN |
|
|
Fuling units 3&4 |
Chongqing |
2x1250 |
AP1000 |
CPI |
|
|
Jingyu units 3&4 |
Jilin |
2x1250 |
AP1000 |
CPI & Guodian |
|
|
Songjiang units 1&2 |
Shanghai |
2x1250? |
AP1000 |
CGN & Guodian |
|
|
Wuhu units 3&4 |
Anhui |
2x1250 |
AP1000 |
CGN |
|
|
Heyuan/Jieyang units 1-4 |
Guangdong |
4x1250 |
AP1000 |
CNNC? CPI? |
|
|
Xiaomoshan units 5&6 |
Hunan |
2x1250 |
AP1000 |
CPI |
|
|
Haiyang units 7&8 |
Shandong |
2x1250 |
AP1000 |
CPI |
|
|
Hengren units 1-4 |
Liaoning |
4x1250 |
AP1000 |
CPI |
|
|
Zhanjiang units 1-4 |
Guangdong |
4x1250 |
AP1000 |
CGN |
|
|
Xiangtan |
Hunan |
4x1250 |
AP1000 |
Huadian? |
|
|
Donggang units 3&4 |
Liaoning |
2x1000 |
|
Huadian? |
|
|
Pulandian units 1-4 |
Liaoning |
4x1250 |
AP1000 |
Huaneng |
|
|
Shizu |
Chongqing |
2x |
|
CNNC |
|
|
Qiaofushan |
Hebai |
2x |
|
CNNC |
|
|
Xianning units 5&6 |
Hubei |
2x1250 |
AP1000 |
CGN |
|
|
Guangshui |
Hubei |
4x1250 |
AP1000 |
CGN |
|
|
Zhingxiang |
Hubei |
4x1250 |
AP1000 |
CNNC, Datang |
|
|
Hebaodao |
Guangdong |
2x |
|
CNNC? |
|
|
Yibin |
Sichuan |
2x1250 |
AP1000 |
CNNC |
|
|
Gulei units 1&2 |
Fujian |
2x100 |
ACP100 |
CNNC-CNEC |
|
|
Hengfeng units 1&2 |
Jiangxi |
2x100 |
ACP100 |
CNNC & Guodian |
|
|
Tongren |
Guizhou |
2x1250 |
AP1000 |
CGN |
|
|
Xiapu |
Fujian |
1x210 |
HTR |
Huaneng |
|
|
Sanming or Xiapu units 3&4 |
Fujian |
2x880? |
BN-800? |
CNNC |
|
|
Jiamusi |
Heilongjiang |
2x1150 |
Hualong 1 |
Huaneng & CNNC, or CGN |
|
|
Subtotal: about 79 units |
|
62x1250 2x1150 8x1000 or? 2x880 1x210 4x100 =90,170 MWe |
|
Total proposed: about 170 | | 194,670 MWe |
|
Hongyanhe, LHNP
This is the first nuclear power station receiving central government
approval to build four units at the same time, and the first in
northeast China. Construction of the first unit of the Hongyanhe nuclear
power plant in Dalian, Liaoning, started in August 2007. It is the
first nuclear power project in the 11th Five-Year Plan, with owner and
operator being Liaoning Hongyanhe Nuclear Power Co, a joint venture of
CGN and CPI (now SPI) – 45% each – with Dalian Construction Investment
Group. It uses CPR-1000 reactors for units 1-4.
The National Nuclear Safety Administration (NNSA) issued a
construction licence for units 3&4 in March 2009, and first concrete
for unit 3 was poured soon afterwards. CGN will be responsible for the
project construction and the operation of the first five years after
commercial operation, with full participation of CPI. The cost of all
four 1080 MWe CPR-1000 units in the first construction phase is put at
CNY 50 billion (US$ 6.6 billion). China Nuclear Power Engineering
Corporation (CNPEC), part of CGN, is managing the project. Shanghai
Electric won a $260 million contract for equipment and Alstom providing
the four low-speed Arabelle turbine-generator sets for $184 million.
Localisation is above 70% for units 1&2 and over 80% for units
3&4.
First power from unit 1 was expected in July 2012, but after delays
over 2011 it started up in January 2013 and was grid connected in
February, with commercial operation in June. Unit 2 started up in
October 2013, was grid connected in November, with commercial operation
in May 2014. Unit 3 started up in October 2014 and was grid connected in
March 2015 (72 months construction) and entered commercial operation in
August. Unit 4 is expected on line late in 2015. The project incorporates a 10,080 m3/day seawater desalination plant using waste heat to provide cooling water.
In May 2010, the NRDC approved preliminary work on the CNY 25 billion
two-unit second phase of the plant (units 5&6), and site work began
in July. The National Nuclear Safety Administration (NNSA) and the
Environment Ministry approved the project in September 2010,
construction start was expected 2011 but following a State Council
announcement and final NNSA construction licence, that for unit 5 was in
March 2015 and for unit 6, July 2015. NDRC approval was reported in
September 2014 and again in February 2015, using ACPR1000 reactors.
Localisation is to be above 80%.
Ningde, NDNP
Construction of CGN's six-unit Ningde nuclear power plant
commenced in 2008. This is on three islands in Fuding city in northeast
of Fujian province, and the first construction phase comprises four
CPR-1000 units. Ningde Nuclear Power Co Ltd (NDNP) was set up in 2006 as
a joint investment of CGN (46%), China Datang Corporation (44%) and
Fujian Energy Group Co., Ltd. The project was approved by the National
Development & Reform Commission (NDRC) in September 2006, and local
content will be about 75% for units 1&2 and 85% for units
3&4. It marks a significant step into nuclear power for Datang.
Construction of the first unit started in February 2008, and it was
grid connected in December 2012 after 58 months. It was declared in
commercial operation in April 2013. First concrete for the second unit
was in November 2008, it achieved criticality in December 2013 and was
grid connected in January 2014, with commercial operation in May.
Construction start for the third was in January 2010 and for the fourth
at the end of September 2010. First criticality for unit 3 was in March
2015, with grid connection two weeks later that month and commercial
operatioon in June. Total cost for four units was put at CNY 52 billion
($7.6 billion). Dongfang Electric is supplying turbine generators for
units 1-4, using Alstom Arabelle low-speed technology, at least for
units 3&4. The pressure vessel and steam generators for unit 1 are
from Dongfang (DFHM), those for unit 2 are from Shanghai Electric (SEC),
those for units 3&4 from China First (CFHI).
In February 2014 the NEA approved preliminary work for units 5&6,
which are set apart from phase 1 units 1-4, with some siting issues to
resolve. CGN has confirmed that they will be Hualong One (HPR1000).
Fuqing
Construction of the six-unit Fuqing nuclear power plant 170 km south
of Ningde also commenced in 2008 at Qianxe, Fuqing city in Fujian,
between Fuzhou and Putian. The Fujian Fuqing Nuclear Co Ltd was set up
in May 2006 with 39% held by China Huadian Corp and 10% by Fujian
Investment & Development Co Ltd. CNNC is responsible for the project
which used CGN's CPR-1000 reactors for units 1-4 since alternatives
were not licensed. CNNC calls these M310+. First concrete for unit 1 was
poured in November 2008, for unit 2 in June 2009, and for unit 3 in
December 2010. Commercial operation is expected over 2014 to 2016. Site
works are under way for further units there, total expected cost for all
six being CNY 88 billion ($14.3 billion). Construction of unit 4
started in September or October 2012, almost immediately after NNSA
authorization. Unit 1 started up in July 2014, was grid connected in
August after 69 months' construction and entered commercial operation in
November. Unit 2 started up in July and was grid connected in August
2015 after 74 months' construction. Units 3&4 are expected in
operation in early 2016 and 2017 respectively.
Construction of the project is by China Nuclear Power Engineering Co.
(CNPE) and the reactor pressure vessels are supplied by China First
Heavy Industries, as for Fangjiashan. In June 2008, Dongfang Electric
Group announced a CNY 5 billion ($725 million) contract for Alstom
Arabelle low-speed steam turbine generators for the Fuqing and
Fangjiashan plants. Units 3&4 have Areva instrument & control
systems.
Late in 2010, CNNC was proposing the CNP1000 for units 5&6,
noting "pre-project under way". In October 2011 CNNC said that units 5
& 6 would be the first ACP1000 units, and in December 2013 it was
announced that they would have Areva-Siemens instrument and control
systems. DEC will supply the steam generators. In January 2014 CNNC said
that they would be CNNC’s first Hualong 1 units. Construction of unit
5, China’s first Hualong One, started in May 2015.
Fangchenggang
The Fangchenggang nuclear power project is located at Hongsha
village, in the Beibu Gulf (Beibu Wan) Economic Zone on the southeast
coast of Bailong Bay in the coastal city of Fangchenggang in the Guangxi
Autonomous Region (45 km from the Vietnam border in south China). It is
sometimes referred to as 'Fangcheng Port' and in ‘Western China’.
Following an agreement in July 2006, the first stage (two 1080 MWe
CPR-1000 units out of six planned) of the plant was approved by NDRC in
October 2008, and again in July 2010. First concrete for unit 1 was
poured in July 2010, and for unit 2, late in 2011. About 87% of the
first two units will be sourced in China.
In October 2009, a general construction contract was signed with
CNPEC. Guangxi Fangchenggang Nuclear Power Co., Ltd., a joint venture
between China Guangdong Nuclear Power Group (61%) and Guangxi Investment
Group (39%), is responsible for the construction and operation. CPI was
earlier involved. The first unit is expected to begin commercial
operation in July 2015, the second a year later. Total budget is CNY 70
billion ($10.26 billion), with CNY 26 billion ($3.87 billion) for stage
1. In December 2011 it was reported that Guangxi was accelerating
construction to relieve power shortage, and allow for exports to
Vietnam. (There is also a Fangchenggang supercritical 2400 MWe
coal-fired power station operated by CLP Guangxi Fangchenggang Power
Company Limited, a 70:30 equity-basis joint venture between China Light
& Power and Guangxi Water & Power Engineering (Group) Co., Ltd.)
CGN from September 2012 planned that Stage 2, units 3&4, should
be the initial ACPR1000 demonstration units, with construction start in
2014. However, no authorization was forthcoming, and since January 2014
these are to be CGN’s inaugural Hualong HPR1000 units, based on CNP1000,
with construction starting at the end of 2015. In May 2015 CGN ordered
the steam generators from DEC, which subcontracted to BWX Technologies
in Canada among others. Cost is put at about CNY 30 billion ($4.9
billion). Stage 3 (units 5&6) is planned as AP1000s.
Yangjiang, YNPS
Yangjiang city in western Guangdong province had originally been
earmarked for the country's first Generation III plants (see section
above on Embarking upon Generation III plants).
After plans changed in the light of pressing generation needs in the
region, Yangjiang will be the second nuclear power base of the China
General Nuclear Power Group (CGN). Development of all six units of the
Yangjiang plant was approved in 2004, with CPR-1000 later confirmed as
the basic technology for it. Local content is about 83% for units
1&2, and is expected to be 85% for units 3&4 and maybe 90% for
5&6 of the evolved design – the first ACPR1000 reactors. Total cost
was expected to be CNY 73 billion ($12.1 billion).
Construction of the first of two CPR-1000 units by CNPEC started in
December 2008. Unit 1 criticality was achieved in December 2013, with
grid connection at the end of the month and commercial operation in
March 2014. Unit 2 was grid connected in March 2015 after 67 months'
construction and entered commercial operation in June.
Construction of unit 3 started in November 2010, unit 4 in November
2012, immediately after NNSA authorization, then the final two (as the
second construction phase) followed from September 2013, with the last
to be built by 2018. Units 3&4 are the first of an improved CPR-1000
design sometimes referred to as CPR-1000+. Unit 3 criticality was in
October 2015. Construction of unit 5 as ACPR1000 began in mid-September
2013 and unit 6 late in December 2013.
Yangjiang 1-6 will be operated under Yangjiang Nuclear Power Co Ltd
(YJNPC) management. In July 2010, Hong Kong-based power utility China
Light and Power (CLP) agreed to take a 17% stake in Yangjiang – the
equivalent of one reactor. However, in September 2013 CGN halted
negotiations with CLP, following delays due China’s review of nuclear
safety. These are expected to resume in 2014, and CLP expects eventually
to take some equity in the plant.
Fangjiashan
Construction of CNNC's Fangjiashan plant started at the end of
December 2008. It is close to the Qinshan plant in Zhejiang province and
essentially an extension of it, using two CPR-1000 reactors, designated
M310+ by CNNC. Construction of the CNY 26 billion ($4.2 billion)
project was by China Nuclear Power Engineering Co. (CNPE) and the
reactor pressure vessels are supplied by China First Heavy Industries,
as for Fuqing. In June 2008, Dongfang Electric Group announced a CNY 5
billion ($725 million) contract for Alstom Arabelle low-speed steam
turbine generators for the Fuqing and Fangjiashan plants. Localisation
is 80%. First criticality of unit 1 was in October 2014 with grid
connection in November and commercial operation in December 2014 and was
grid connected in mid-January 2015. Unit 2 started up in December 2014,
with grid connection in mid-January 2015 and commercial operation in
February. The project is 72% owned by CNNC, with the remainder held by
Zhejiang Provincial Energy Group Co Ltd. The two units bring the Qinshan
total effectively to nine, with 6540 MWe.
Sanmen
At the end of 2006, the Westinghouse AP1000 reactor design was
selected for Sanmen in Zhejiang province (and for Yangjiang in Guangdong
province, with the latter site changed to Haiyang). Contracts with
Westinghouse and Shaw for two units were signed in July 2007. Site works
under CNNC commenced in February 2008 and an engineering, procurement
and construction (EPC) contract was signed in March 2009 between SNPTC +
CNNC and China Nuclear Engineering & Construction Group (CNEC) for
both units, which will be overseen by Westinghouse and Shaw (now
CB&I). Other stakeholders are Zhejiang Provincial Energy Group Co
Ltd, CPI Nuclear Power Co Ltd, and China Huadian Corp.
Construction on Sanmen 1 – the world's first AP1000 unit – officially
commenced on 19 April 2009. The pressure vessel, from Doosan, was
installed in September 2011. The reactor was expected to begin operation
in December 2014 with unit 2 less than a year later. Construction on
unit 2 commenced in mid-December 2009. The pressure vessel and steam
generators for unit 2 are being made in China. MHI supplied the turbine
generators for both units. CNEA in 2013 said the cost would be about
$2610/kW. In March 2014 NNSA said that start-up would be delayed to
December 2015 due to design changes and problems with the US-supplied
main coolant pumps which created further delay. Following successful
tests, the modified pumps are being shipped from Curtis-Wright to site
in October 2015, and SNPTC predicts commercial operation in September
2016. See section on Embarking upon Generation III plants above.
Another six units are envisaged for the Sanmen site.
Haiyang
Shangdong Nuclear Power Company (a subsidiary of CPI) signed
contracts with Westinghouse and Shaw for two AP1000 units in July 2007.
First concrete was poured in September 2009 for unit 1 and June 2010 for
unit 2. The 5000 cubic metre base mat of each was placed in a single
pouring of less than 48 hours. The pressure vessel and steam generators
for unit 2 are being made in China. MHI supplied the turbine generators
for both units. These units were expected to commence operation in
December 2014 and March 2015, but in March 2014 NNSA said that start-up
would be delayed into 2015 due to design changes and component problems.
However, problems with the US-supplied main coolant pumps may delay
operation to 2016 or 2017. See section on Embarking upon Generation III plants above.
The site will eventually have six or eight units, and in March 2009,
the NDRC approved preliminary works for units 3&4 at the CPI
site. In February 2014 the MEP approved construction start on these,
which are expected to cost CNY 31.4 billion ($5.1 billion).
Haiyang will be a CPI training base for AP1000 staff, along with a set-up at Yantai.
Taishan
The first two EPRs planned for Taishan in Guangdong province form
part of an €8 billion contract signed by Areva and the China General
Nuclear Power Group (CGN) in November 2007. The Taishan project
(sometimes referred to as Yaogu) is owned by the Guangdong Taishan
Nuclear Power Joint Venture Company Limited (TNPC), a joint venture
between EDF (30%) and CGN. First concrete was poured in October 2009,
and unit 1 is expected to be commissioned in 2016, with unit 2 a year
later. Areva is sourcing the main components for both units from Japan
and China and expects net capacity to be 1660 MWe each. See section on Embarking upon Generation III plants above.
Site works are reported to be proceeding for units 3&4.
Shandong Shidaowan HTR-PM
A demonstration high-temperature gas-cooled reactor plant, with twin
reactor modules driving a single 210 MWe steam turbine, was initially
approved in November 2005, to be built at Shidaowan (Shidao Bay) in
Weihai city, Shandong province, by Huaneng Shandong Shidaowan Nuclear
Power Company Ltd (HSNPC). It will be part of the Rongcheng Nuclear
Power Industrial Park project. The HSNPC joint venture is led by the
China Huaneng Group Co – the country's largest generating utility but
hitherto without nuclear capacity, and still without NNSA authority to
build nuclear plants itself. Huaneng Power International is investing
CNY 5 billion in the project, which received environmental clearance in
March 2008. An important 20% stake in the project is held by Tsinghua
University INET, reflecting its innovative technology, and 32.5% is held
by CNEC, which is promoting commercial HTR versions. With site work
complete, following NDRC approval construction started in mid-2011.
Commercial operation is expected in 2017. (information on CGNPC and
Tsinghua web sites) NB though involving twin reactors this is shown as a
single reactor unit in WNA Tables.
The EPC (engineering, procurement, construction) contract was let in
October 2008, and involves Shanghai Electric Co and Harbin Power
Equipment Co. A simulator contract signed in May 2010 was between HSNPC,
Chinergy and CGNPC Simulator Co. In November 2010 Huaneng Group signed
an agreement with US-based Duke Energy to train nuclear plant staff.
After three years of negotiation, in March 2011 a contract was signed
with SGL Group in Germany for supply of 500,000 machined graphite
spheres for HTR-PM fuel by the end of 2013. A new HTR fuel production
plant is being set up at Baotou.
This will be the demonstration plant for a larger commercial plant at Ruijin, Jianxi province. (See below, also Research and development section in page on China's Nuclear Fuel Cycle.)
Shidaowan PWRs
In November 2007, China Huaneng Group (CHNG)
signed an agreement with CGN for the Huaneng Nuclear Power Development
Co Ltd to build four CPR-1000 reactors at Shidaowan, Rongcheng, Weihi
city, in Shandong province in an $8 billion deal. A letter of intent
regarding the first two was signed in 2008. The project then became
focused on the CAP1400, with SNPTC as the lead partner and two CAP1400
reactors as phase 1.
The State Nuclear Power Demonstration Plant Company (SNPDP) is a
55-45% joint venture company set up in December 2009 by SNPTC and China
Huaneng Group (CHNG) to have overall responsibility for building and
operating the first CAP1400 reactors and subsequent CAP1700 reactors
(see Reactor technology section above), two CAP1400s being envisaged as demonstration units at Shidaowan. SNPTC will be in charge of building these.
The Environment Impact Assessment Report (EIAR), the Site Safety
Assessment Report (SSAR) and construction application were submitted to
Ministry of Environment Protection and NNSA in March 2012, and NNSA
approval of both was expected in mid-2014. Site works for the first two
CAP1400 units totaling 3.24 GWe were complete by April 2014. First
concrete for unit 1 was expected in April 2015, with 56-month
construction giving operation in December 2019. Unit 2 first concrete is
due in August 2015 and operation in 2020.
In June 2014 the Ministry of Environment Protection was seeking
comment on SNPTC plans for CAP1400 units 3&4, expected to cost CNY
42.3 billion. However, Huaneng, which owns the Rongcheng Industrial Park
site, is keen to build four AP1000 units as phase 2, and this is now
the plan. The eventual capacity of Shidaowan over 20 years is expected
to be very large.
Bailong
This is a CPI project about 30 km from Fangchenggang in Guangxi
province, with two AP1000 reactors in stage 1 and two more in stage 2.
It is reported to be delayed by local opposition, and may be an
alternative to stage 3 of Fangchenggang.
Huizhou
This is a CGN project in Huangbu town, Huidong county, Huizhou city
on Red Bay close to Daya Bay, with two AP1000 reactors in its first
stage and four more to follow. Initial investment by CGN and Huizhou
city was estimated at CNY 80 billion in 2011. The project company is
China Guangdong Huizhou Nuclear Power Co. The project passed its initial
feasibility assessment by the provincial Development and Reform
Commission in 2011. Some site works have been undertaken.
Tianwan Phases II, III & IV
In October 2006, a preliminary agreement for two further 1060 MWe
AES-91 VVER reactors as the second construction phase at Tianwan in
Lianyungang city of Jiangsu province was signed with Russia's
Atomstroyexport. Preliminary approval from NDRC was received in August
2009, and the project was then expected to cost $3.8 billion. Protracted
discussion on pricing for the Russian components of the plant delayed
the project. Eventually, a contract for the engineering design of units
3&4 was signed in September 2010 between Jiangsu Nuclear Power
Corporation and Atomstroyexport, and the general contract came into
force in August 2011 with protocol signed by China Atomic Energy
Authority and Rosatom. Final approval from NDRC was received in January
2011. The EPC contract with CNNC's China Nuclear Engineering &
Construction Group (CNEC) was signed in October 2011. A civil
engineering contract was let to China Nuclear Industry Huaxing
Construction Company (HXCC) in May 2012, and to China Nuclear Industry
23 Construction Co for component installation in July. Both are CNEC
subsidiaries. An intergovernmental protocol was signed in December 2012,
with first concrete poured that month. In August 2013 the China
Development Bank signed a loan agreement with Jiangsu Nuclear Power Co.
for CNY 16 billion for phase II.
Atomstroyexport is providing 30% of the V-428M phase II units for
€1.3 billion, including nuclear island equipment (reactor, steam
generators, pressurisers, primary piping. etc.) and some related
equipment. It is not acting as the principal contractor, though it
insists on retaining intellectual property rights. Jiangsu Nuclear Power
Corporation is responsible for about 70% of the project, namely, the
civil work, turbine island with equipment and related infrastructure on
the site. Iskorskiye Zavody, part of OMZ, is supplying the major
components covered by the Russian €1.3 billion part of the phase II
plant. This includes two reactor pressure vessels with internals and
upper units. Delivery was to be completed in 2014. (The company already
took part in making the major equipment for Tianwan 1&2, including
reactor pressure vessels.) ZiO-Podolsk is making the steam generators –
the third arrived on site in March 2015. The turbine generator sets will
probably be sourced from Dongfang Electric, using Alstom Arabelle
low-speed technology. Areva I&C systems are being used.
First concrete for unit 3 was poured in December 2012, and that for
unit 4 in September 2013. Commercial operation is due in 2018 and 2019.
There has been some confusion about the technology for phase III,
units 5&6. Due to urgency in meeting power demands, it appeared
likely that units 5&6 (phase III) might be built ahead of 3&4,
as CPR-1000 units, based on those at Fangjiashan. This technology
prospect appeared to lapse with post-Fukushima sidelining of the design.
But the CNNC website in October 2014 had them as 1000 MWe units,
consistent with the 2012 decision to build as CPR-1000. An EPC contract
between Jiangsu and CNPE was signed in February 2011, making CNPE the
project manager, but saying then that Units 5&6 were likely to be
VVER-1200s. Dongfang Electric has a contract to supply turbine
generators using Alstom Arabelle low-speed technology.
Phase IV is less ambiguous. In December 2012 Russian sources reported
discussions with CNNC regarding phase IV of Tianwan (units 7&8),
using VVER technology. In October 2013 China National Nuclear Power Co
Ltd (CNNP) said that the technology might be VVER-1200/AES-2006 rather
than VVER-1000/AES-91. Atomernergoproekt has quoted Leningrad’s V-491
reactors as reference units for later Tianwan units, now apparently just
7&8. In October 2014 Russia’s energy minister said that he expected
Atomstroyexport to supply units 7&8 at Tianwan.
Changjiang
CNNC's Changjiang nuclear power plant on Hainan Island started
construction in April 2010 for operation in 2015. It will eventually
comprise four 650 MWe PWR units based on those at Qinshan Phase II.
Total cost of the first pair of CNP-600 units is put at about CNY 20
billion ($2.8 billion). Unit 1 criticality was in October 2015. Units
3&4, probably ACP600, will be built as the second phase of
construction from 2018. Huaneng Power International (HPI), part of China
Huaneng Group (CHNG), holds a 49% share in Hainan Nuclear Power Co Ltd.
More than 70% of the plant's equipment is to be made in China.
Xudabao
CNNC's Xudabao or Xudapu nuclear power station is in Xingcheng City,
Huludao (Hulu island), in coastal Liaoning province. The CNY 110 billion
(US$18 billion) Xudabao project will comprise six AP1000 or CAP1000
reactors, with units 1&2 in the first phase. Site preparation was
under way in November 2010, and NNSA granted site approval for two units
in April 2014. Final approval was reported in September 2014, and
operation was due in May 2018, according to CNECC.
CNNC's Liaoning Nuclear Power Company Ltd owns the plant, with Datang
International Power Generation Co holding 20% equity, and State
Development and Investment Corporation (SDIC) 10%. The general
contractor is China Nuclear Power Engineering Company Ltd (CNPE), and
negotiations for an EPC contract for units 1&2 were taking place in
December 2011. In October 2010, the Northeast Electric Power Design
Institute (NEPDI), Changchun, Jilin, a subsidiary of China Power
Engineering Consulting Corporation (CPECC), signed a survey and
engineering contract for the plant. When Taohuajiang plant was deferred,
the main reactor parts were transferred to Xudapu. Manufacture of the
steel containment was launched in July 2013 by Shandong Nuclear Power
Equipment Manufacturing Co Ltd (SNPEMC).
Lufeng
CGN Lufeng Nuclear Power Corporation is making efforts to start on
the first two units (of six) of the Lufeng (Shanwei) plant in the
Tianwei district in eastern Guangdong. An EPC contract was signed with
SNERDI in September 2013, environmental approval was in June 2014, and
NDRC approval for two AP1000 units was reported in September 2014. It
will be a CNPEC project. It is in the 12th Five-Year Plan, site work is
under way and construction start in 2015 is expected. The AP1000 plant
equipment manufactured for Xianning is being deployed there for units
1&2, and it will be CGN's first AP1000 plant. Investment to June
2014 was CNY 37.4 million. Commercial operation is expected in 2019 and
2020.
Putian & Zhangzhou-Gulei
China Guodian's first nuclear power venture, with CNNC holding 51% of
CNNC New Energy Corporation, will initially have two small modular
ACP100 reactors, at Putian on the coast in Fujian province, near Xiamen,
as a demonstration plant. These are integral PWRs, with passive cooling
for decay heat removal. This will be the CNY 5 billion ($788 million)
phase 1 of a larger Zhangzhou project. CNNC said that the units could
provide electricity, heat and desalination. Construction time is
expected to be 36-40 months, starting 2015. It involves a joint venture
of three companies for the pilot plant: CNNC as owner and operator, the
Nuclear Power Institute of China as the reactor designer and China
Nuclear Engineering Group being responsible for plant construction.
A second proposal is for two ACP100 units on the other side of the
peninsula, at Zhangzhou-Gulei, but though approved by SASAC in November
2011, it is stalled due to opposition from local government. CNNC New
Energy Corporation (CNNC & Guodian) is seeking alternative sites.
Zhangzhou
The larger project will be undertaken by Nuclear Guodian Zhangzhou
Energy Co. Ltd., and will comprise four AP1000 reactors as phase I and
two more as phase II. CNNC says it has received preliminary approval,
and in May 2014 local government gave approval, with phase 1 costing CNY
54.4 billion. The company was established in November 2011, by CNNC or
China Nuclear Power International Inc (51%) and China Guodian
Corporation (49%). The proposal was submitted to NDRC in August 2010.
Hongshiding (Rushan)
In November 2006, an agreement was signed by CNNC to proceed with the
first two units of the Hongshiding nuclear plant at Hongshiding in
Weihai or Rushan city, Shandong province, costing $ 3.2 billion, with
construction to begin in 2009 and first power in 2015. However, it has
been deferred. Six units now likely to be Hualong 1, 1150 MWe each, are
envisaged at the site, with Shandong Hongshiding Nuclear Power Co. Ltd
as developer.
Lianyungang
CGN has several plans in Northern China, and among other possible
projects it has applied for several reactors at Lianyungang, Jiangsu
province, very close to CNNC’s Tianwan plant. A proposal has been
submitted to the NRDC. However, the further development of Tianwan makes
it unlikely, and if implemented, it will not proceed before about 2025.
It is not included in the above Table or any statistics.
Songjiang
This is to be developed in Shanghai's Songjiang district by CGN with
China GD Power Development Co Ltd, a subsidiary of Guodian, and in
connection with a framework cooperation agreement with the State Grid
Corporation of China. It is not expected to be approved before about
2020.
Sanming
In October 2009, an agreement was signed by CIAE and CNEIC (a CNNC
subsidiary responsible for technology imports) with Russia's
Atomstroyexport to start pre-project and design works for a commercial
nuclear power plant with two BN-800 fast neutron reactors (referred to
as Chinese Demonstration Fast Reactors) at Sanming city, an inland part
of Fujian province. A site survey and preliminary feasibility study had
been undertaken in 2007-08. CNNC in April 2010 established Sanming
Nuclear Power Co Ltd as a joint venture company with the Fujian
Investment & Development Corp and local government, and initiated a
full feasibility study.
Construction was due to start in 2013, once an intergovernmental
agreement was in place, expected in 2012, but now apparently suspended
indefinitely. The local content was targeted at 70%, and the first unit
was to be in operation in 2018, with the second following about a year
later. A second phase, with units 3&4, was due to commence in 2015.
The plant would be similar to the OKBM Afrikantov BN-800 design built in
Russia at Beloyarsk 4, which started up in 2014, though this is
actually an experimental reactor rather than commercial
type. Negotiations on price earlier delayed the project and
NIAEP-Atomstroyexport then said it expected the first contracts to be in
place at the end of 2014. However, it appears that China's policy
regarding fast reactors remains uncertain, and the first commercial
demonstration units are now not expected to be on line before 2025.
Inland nuclear power plants
These have been delayed significantly from the dates for the larger
units planned before mid-2011. This was announced as being due to
concerns regarding possible pollution of rivers. Taohuajiang, Xianning
and Pengze are all in the 12th five-year plan to start construction, but
the premiere's announcement in October 2012 deferred approvals for
inland plants until after 2015. The delay has involved an assertion of
central government control over eager provincial governments with their
own economic development agendas. NEA approvals are likely to start for
these in 2016.
In September 2014 three projects were mentioned as likely first
construction starts for 13th five-year plan from 2016: Taohuajiang in
Hunan, Pengze in Jiangxi, and Dafan in Hubei.
In June 2015 CNNC signed a strategic cooperation agreement with
Sichuan provincial government to promote “large-scale commercial nuclear
power reactors and renewable energy generation, nuclear power equipment
manufacturing, nuclear technology and innovation platform
construction.” Sichuan had earlier promoted Nanchun as a power plant
site, and CGN is involved with this – see below.
In September 2015 it was reported that 31 inland sites had cleared
preliminary approval by NDRC, and awaited State Council approval.
Taohuajiang
CNNC's Taohuajiang nuclear power plant on the Zi River in Taojiang
county,Yiyang city, near Yueyang in inland Hunan province is likely to
be China's first inland nuclear power plant. It was expected to start
construction in September 2010, and some CNY 3 billion of site works are
complete, but construction is delayed to 2015 or 2016. (It is also
referred to as the Taohua [peach blossom] River project.) CNNC set up
Hunan Taohuajiang Nuclear Power Co Ltd. to build and operate the plant.
Initially this was to be 4x1000 MWe at a total cost of CNY 34 billion,
but it is now to be a four-unit CAP1000 project costing over CNY 70
billion. The main contractor is China Nuclear Industry 23rd Construction
Co Ltd; China Erzhong is contracted to supply the main pressure vessel
forgings, and Dongfang Electric Corp will supply other major components.
Germany's GEA Group is to construct the cooling tower for unit 1: a
natural draft unit some 200 metres high and 160 m in diameter, with
15,000 square metres drenching area. Subsequent towers will have
increasing local content.
The project was approved by the NDRC in November 2005, and in 2008
the project was approved for preliminary construction. Site works have
been undertaken to the extent of CNY 3.8 billion. The design by SNERDI
under SNPTC and SNPDRI was submitted to the NNSA in February 2010 for
licensing. A general framework agreement for construction was signed by
CNNC with CNPE Corporation as EPC contractor in December 2010. The first
unit was originally expected in commercial operation in 2015, and the
fourth in 2018. However, after all the inland projects were deferred the
reactor components were transferred to Xudapu/Xudabao, and the site
workforce was laid off. Construction start is now expected in 2016.
Xianning/Dafan
In August 2008, CGN and Hubei Energy Group Ltd set up the Hubei
Nuclear Power Company as a joint venture and announced plans to build a
nuclear power plant at Dafan in Xianning city of the inland Hubei
province. Site works for this plant (four AP1000 units) have been
undertaken to the extent of CNY 3.4 billion. Construction of the first
two units was expected to start in 2011, but is delayed to 2016. The
reactor pressure vessel for the first unit is contracted to China First
Heavy Industries, and the first two 209 metre high cooling towers to
Belgium's Hamon Thermal. The cost of four AP1000 reactors is put at CNY
60 billion ($8.8 billion). This would have been CGN's first AP1000
plant, but the equipment has been reassigned to Lufeng. A further phase
is estimated to cost CNY 45 billion.
The large pre-assembled modules that will make up the bulk of the new
AP1000s are to come from a new inland facility owned by new firm Hubei
Nuclear Power Equipment Company.
Reports of a Songzi plant may refer to later stages of Dafan, though possible projects in Yangxin county have been mentioned.
The Hubei Nuclear Power Co is also reported to be planning a
four-unit AP1000 plant at Guangshui city in the northeast of the
province.
Pengze
CPI's Pengze Nuclear Power Project in Jiangxi province is to have
four AP1000 reactors costing CNY 60 billion ($8.8 billion). The site has
been prepared for the first two units, and safety and environmental
approvals were obtained in May 2009. CPI signed the EPC contract
framework for phase 1 (units 1 & 2) in August 2009, the engineering
project contract was reported to be between CPI Jiangxi Nuclear Power Co
Ltd and CPIC. The equipment procurement was reported to be between CPIC
and China Power Complete Equipment. CPI aimed to start construction in
2010, for 2013 start-up, but construction has been delayed, evidently to
2016. Site works amount to CNY 3.4 billion.
The project is inland in Juijiang city, across the Yangtze River from
Wangjiang in Anhui province. The cooling towers are being designed by
Belgium's Hamon Thermal for the State Nuclear Electric Power Planning
Design and Research Institute (SNPDRI). The project has been opposed by
Wangjiang in neighbouring Anhui province, which has plans for several
nuclear plants iteself, including Wuhu (Fanchang) and Jiyang (Chizhou),
with Anqing Congyang and Xuancheng along the Yangtze River also
mentioned.
Wuhu
The Wuhu nuclear plant on the Yangtze River in the Bamaoshan area,
Fanchang county, of Anhui province was planned to have four 1000 MWe
CPR-1000 units, but is now designated for AP1000s to be constructed in
two phases. CGN's proposal for two units of phase 1 has been submitted,
some preparatory work has been undertaken and the Anhui Wuhu Nuclear
Power Co has been set up, with 51% CGN ownership. The environmental
impact statement was released for public comment in January 2010.
Ningdu/Ganzhou
CNNC New Energy Corp, the joint venture of CNNC (51%) and Guodian
Corp, has also signed a preliminary agreement for small modular reactors
with Ganzhou city in Jiangxi province.
Xiaomoshan
The Xiaomoshan nuclear power plant on the Yangtze River in Huarong
county, Yueyang city, Hunan province (inland), is a priority project for
CPI. It will eventually have six AP1000 reactors and be built by Hunan
Nuclear Power Company Ltd in two phases. NDRC approval was given in 2006
but as of mid-2010 NNSA approval was awaited. Site preparation has been
undertaken and first concrete was expected late in 2010. The cost is
put at CNY 70 billion ($10.25 billion) for the first four units, funded
by SNPTC and Wuling Electric Power Development Co. (a CPI subsidiary).
The Heimifeng pumped storage plant will be associated with it.
Yanjiashan/Wanan/Ji'an
In August 2009, CNNC (51%) signed a joint venture agreement with
Jiangxi Ganneng Co. Ltd and Jiangxi Ganyue Expressway Co Ltd (49%
between them) setting up Jiangxi Nuclear Power Co to build the Wanan
Yanjiashan nuclear power project at Ji'an in the Jiangxi province. CNNC
contracted a feasibility study of Yanjiashan nuclear power program in
July 2010. Pre-project work was reported as under way in November 2010.
(This is also reported as a CPI project.)
Shaoguan
CGN's Shaoguan nuclear plant will comprise four AP1000 reactors and
is expected to cost RMB 50 billion. It will be located in Baitu Town of
Qujiang District in Shaoguan City, and will be the first inland nuclear
power project in Guangdong. The Shaoguan Nuclear Power Co was
established in April 2010.
Zhongxiang
CNNC's Hubei Zhongxiang nuclear power project is at Zhongxiang city
in central Hubei, with China Datang. The 5000 MWe plant is undergoing a
detailed feasibility study, but further details are unknown.
Cangzhou
China Huadian plans the Cangzhou Haixing nuclear plant with six
AP1000 reactors in Cangzhou city, Hebei province, 90 km inland from
Tianjin. A CNY 100 billion investment is envisaged by the China Nuclear
Huadian Hebei Nuclear Power Co. CNNP has 51% of the project company,
Huadian Power International 39% and Jinto Energy Investment 10%. Initial
investment in the two-unit first stage is CNY 8.443 billion ($1.36
billion). In April 2014 the NEA approved the project and ordered site
selection to begin, focused on Xiaoshan and Bianzhuang.
Hengfeng/Shangrao
CNNC New Energy Corp, the joint venture of CNNC (51%) and China
Guodian Corp, has also signed an agreement for small modular reactors
with Hengfeng county, Shangrao city in Jiangxi province.
Nanchun/Nanchong/Sanba
In 2005, Sichuan province proposed Nanchun/Nanchong city east of
Chengdu as a suitable site for a nuclear power plant and sought approval
for it from the National Development and Reform Commission (NDRC),
which was not given, possibly because of seismic concerns. In March
2009, the provincial government signed an agreement with CGN to pursue
the plan for a Nanchun nuclear power plant, involving the Nuclear Power
Institute of China (NPIC), headquartered in Chengdu. Preliminary plans
in 2008 were for a 4000-6000 MWe Sanba nuclear power plant on the
Jialing River, at a cost of CNY 25 billion ($3.7 billion), but four
Hulaong One units are now proposed. Majority ownership would be CGN.
Another Sichuan agreement for a nuclear power plant project has been signed between CNNC and Yibin city, south of Chengdu.
Xiangtan
In December 2009, China Huadian Corp signed an agreement with
Xiangtan city government in Hunan to undertake studies for a CNY 60
billion power plant comprising four 1250 MWe reactors. A refined
proposal was expected in September 2010. This will apparently be the
fourth nuclear project for China Huadian.
Longyou/Zhexi
In October 2008 a project proposal was submitted to NDRC by CNNC and
Zhejiang Energy Group Co Ltd for a nuclear power plant in Hangzhou,
western Zhejiang province, with four AP1000 reactors, though earlier
reports had four 1000 MWe units to be built in two phases from late
2010. The proposed site is Tuanshi, Longyou county. Pre-project work was
reported as under way in November 2010.
Jingyu
CPI plans to spend CNY 85 billion to build the six-unit Jingyu or
Chisong nuclear power plant in Jingyu county near Baishan, in southern
Jilin province, with four AP1000 units to be in stage 1. The project is
still in the preliminary feasibility stage, though site preparation is
under way. Construction start was scheduled for 2012.
Nanyang
To be a six-unit CNNC or CPI plant in Henan province. Pre-project work was reported as under way in November 2010.
Tongren
In July 2014 Guizhou province announced that it had contracted with
CGN to build two 1250 MWe reactors at Tongren city for CNY 35 billion,
by 2020. The site is being decided among Dejiang, Sinan and Yanhe
counties. CGN has also agreed to build two 100 MWe nuclear units for CNY
3 billion, and a 1000 MWe wind farm for CNY 5 billion.
The following inland plants have been proposed but are not understood to be under active consideration in 2015:
Jiutai, Liangjiashan
These two nuclear power plants planned for northern Jilin province
close to Changchun, were to be developed by CGN with China GD Power
Development Co Ltd, a subsidiary of Guodian, and in connection with a
framework cooperation agreement with the State Grid Corporation of
China. They are not expected to be approved before about 2020.
Jiyang
Besides Wuhu, CNNC was reported as starting a feasibility study on
another four-unit nuclear plant in the Anhui province, at Jiyang in
Chizhou city, in December 2008.
Hengyang
In August 2009, CNNC signed an agreement with Hengyang city in Hunan
province to build a nuclear power plant there or nearby. This is about
200km south of its Taohuajiang project at Yiyang city in Hunan. China
Guodian Corporation, one of the country's largest power producers, is
involved in the project.
Ruijin
In April 2015 CNEC announced that its proposal for two commercial 600
MWe HTR units at Ruijin city in Jiangxi province had passed an initial
feasibility review. The design is based on work by Tsinghua university,
taking shape as the Shidaowan HTR-PM of 210 MWe. Each 600 MWe unit will
have three such modules. Ruijin Nuclear Engineering HTR NPP Co, Ltd was
established in November 2014. CNEC and the provincial government will
apply to NDRC for approval, and hope to start construction in 2017 for
grid connection in 2021.
Further Information
Notes
a. According to the China Electricity Council, electricity
consumption in 2010 increased 14.6% to 4190 billion kWh, corresponding
with a 10% growth in gross domestic product (GDP). Some 3090 billion kWh
of this was in industry. China's energy consumption per unit of GDP met
a target reduction of 20% from 2005 levels by the end of 2010,
according to the National Development and Reform Commission (NDRC). The
energy intensity targets for the following five years are expected to be
about 17%. [Back]
b. The CNP series of reactors is also referred to as the CP series. [Back]
c. The ACP600 design appears to be an advanced version of the
CNP-600. CNNC expects to complete development of the ACP600 design by
2013. [Back]
References
1. Cost of Pollution in China: Economic Estimates of Physical Damages, The World Bank, State Environmental Protection Administration, P. R. China (February 2007) [Back]
2. Platts Power in Asia, 21 January 2010; China's electricity consumption jumps 14.56% in 2010, Xinhua News Agency (17 January 2011) [Back]
3. International Energy Outlook 2009, Energy Information Administration, U.S. Department of Energy, DOE/EIA-0484(2009), available at www.eia.doe.gov/oiaf/ieo/index.html [Back]
4. Maintain nuclear perspective, China told, World Nuclear News (11 January 2011) [Back]
5. APWR and HTR are listed into the national program, CNNC news release (24 February 2006) [Back]
6. Criticality for fast reactor World Nuclear News (22 July 2010) [Back]
8. Unit 3 at Qinshan Phase II Nuclear Power Station begins operation People's Daily Online (22 October 2010) [Back]
General sources
China General Nuclear Power Group website (www.cgnpc.com.cn)
China National Nuclear Corporation website (www.cnnc.com.cn)
Country Analysis Briefs: China, Energy Information Administration, U.S. Department of Energy, available at http://www.eia.doe.gov/emeu/cabs/index.html
Uranium 2007: Resources, Production and Demand, OECD Nuclear Energy Agency and International Atomic Energy Agency, 2008 (ISBN: 9789264047662)
Nicobar Group website (www.nicobargroup.com)
Dynabond PowerTech website (www.dynabondpowertech.com)
Proceedings of the World Nuclear Association's China International Nuclear Symposium, held in Beijing on 23-25 November 2010, and that in Hong Kong in October 2011
Xu Yuming, May 2013, CNEA presentation: China’s nuclear power development in post-Fukushima era
An Analysis of China’s INDC, Fu Sha et al, China National Center for Climate Change Strategy and International Cooperation (NCSC), 2 July 2015